The latest progress of the parallel section of the male business and the Lunan high -speed rail is expected to start the road base construction in August
Author:Heze Daily Time:2022.06.15
As the second high -speed rail in our city, the parallel section of the high -speed rail and the Lunan high -speed railway has started construction in the early stages of last year. On June 14, the reporter visited the construction site again and learned that the parallel section of the male business and the Lunan high -speed railway is expected to start the road -based construction in August.
On the morning of the same day, after the registration review, after wearing construction work clothes and a hard hat, the reporter followed the project in charge of the project into the construction area.
On the north side of the station building of Hezong Zedong Station, on the three 7 -line areas set up for the high -speed rail field for the high -speed railway, the third platform can be seen on the platform soil floor supported by the pre -pressed template support, along the slope, there is a reinforced steel bars on both sides. Exposing the ground.
In the construction area below the two platforms, the workers are cooperating with the excavation machine to excavate the ditch attached to the platform. The supervisors are supervised at the construction office.
Below the west side of the pre -pressure layer where the reporter is located, the workers are driving a small road pressure machine to set the platform foundation and crushed. On the top of the head, the construction of the construction of the station in Hezong Zedong Station was cleaned up and installed on the duty sheds of the Xiong Shopping Mall.
Near 11 o'clock, the temperature in the construction environment rose, and the workers took off their posts to the rest area.
Knowing that he was going to be interviewed, the worker Sha Ronglin quickly wiped the sweat on his face, and tied the work of the upper body as much as possible. The dark and rough face showed a solid smile.
Sha Ronglin told reporters that his hometown has been in Jiangsu to participate in the construction of the high -speed rail for 4 years. "In the past, we built the Lunan high -speed rail, and later built the parallel section of the high -speed rail and the Lunan high -speed rail. I can come to Heze and have been participating in the construction of the high -speed rail here. I think it is proud!" He said with a smile.
According to Yang Zehua, the chairman of the Fifth Sub -Ministry of the Paying Section Project of the Tenth Railway in the Construction Fangzhong Railway (with the Lunan High Speed Rail), the Lunan Xiongs Commercial Simultaneous Implementation Engineering Station is a total of 3.3 kilometers in front of He Zedong Station. Some have been under construction, the overall progress of the station project has been completed by more than 90%, and the construction of the road base bed is to be uninstalled after pre -pressure. At present, it has been pre -pressed for about 4 months. It is expected that the road base construction will be fully opened in August.
"Under the high temperature environment in summer, it is not suitable for construction after 11 noon and before 3 pm. For this reason, we adjust the construction time in time. Workers get off work at 11 noon, and then go to get off work at 3 pm or 4 pm. The next night's get off work time. And as in previous years, we provided workers with heatstroke and cooling materials, and paid attention to the health of workers in time. While not delaying construction, we made every effort to protect the rights and interests of migrant workers. "Yang Zehua said.
Heze Newspaper All Media Reporter Yun Hua
- END -
1317 storage households were given a red code, and 5 officials were accountable scholars: public power must not be abused
Public power must not be abusedRecently, the Fu Red Code incident has aroused wide...
Care about care and service talents Changzhi issued "Ten Measures"
Shanxi Evening News (Reporter Zhang Wenju) In order to increase the care and care of the majority of talents, a few days ago, Changzhi City issued the Ten Measures of Changzhi Caring for the Talents