40 ° C at high temperature per hour!They climbed up to 50 meters high equipment to find safety issues
Author:Zhejiang Daily Time:2022.07.14
Zhejiang News Client Reporter Xu Tiancheng Sharing Alliance Yuecheng Station Yan Liming Jiang Chenxi
At 10 am on the 13th, in the production park of Zhejiang Shaoxing Sanyuan Petrochemical Co., Ltd., located in Yuecheng District, Shaoxing City, Zhu Tianlong, an operator of 450,000 tons of PDH propionide dehydrogenide dehydrogenide dehydrogenide dehydrity Long -sleeved work clothes, put on a helmet, and started the inspection work of the "10 o'clock" on the day.
"The two groups of personnel switched alternately, tour every hour, and one hour." Before departure, Zhu Tianlong first poured a bottle of mineral water to supplement the water required for the next hour.
At this time, the outdoor temperature of Shaoxing has been nearly 40 ° C. The scorching sun is the first, only from the entrance of the park to the device response area, it is enough to make people sweat. "Let's go to the highest point to check!" Zhu Tianlong issued an experience invitation to us at the top floor of the device at nearly 50 meters high.
The 450,000 -ton PDH propine dehydrogenation is one of the three most important devices in the three -circular petrochemical production park. It takes out the hydrogen in the propane in a special catalyst at a high temperature state to generate the polypropylene propylene propylene propylene, Essence "The temperature in the device reactor exceeds 600 ° C, and the outer temperature of the device measured by the dedicated temperature measuring instrument is also as high as 500 degrees Celsius. When the inspection is close to these reaction areas, there will be obvious burning sensation." An inspector Say.
At the scene, the workers used professional tools to check the operating conditions of each detection point. Whether the current is normal, whether the temperature and oil level are normal, whether the equipment vibration conditions are normal, the pipeline connector is leaked ... Every time there is a pipeline interface ... Every time there is a pipeline interface ... Every time there is a pipeline interface ... Every time there is a pipeline interface ... Every time there is a pipeline interface ... Every time there is a pipeline interface ... Every time there is a pipeline interface ... Every time there is a pipeline interface ... Every time there is a pipeline interface ... Every time there is a pipeline interface ... Every time there is a pipeline interface ... Every time there is a pipeline interface ... They tested each matters according to the program. After confirming that they were correct, they moved the digital disk on the card inspection card from "9" to "10". "This means that the" 10 point "period has been inspected and everything is normal." Zhu Tianlong introduced.
When climbing a layer and one layer, with the workers to the 48 -meter -high inspection point, the time has passed nearly half an hour. The clothes of the peers have almost been wet with sweat, and their faces are hot and red. Here, we encountered Zhu Weigang, deputy president of Sanyuan Petrochemical production, which is being sampling, "The temperature of the handrail railings on the top now has reached 46 ° C, and the inspection workers are really hard." He said that the importance of equipment inspection is not the importance of equipment inspection work. In the case of, "the production safety responsibility of chemical enterprises is more important than Taishan. Even if it is only a small leakage problem at the device connection, it may cause fire and cause safety accidents. Especially the current high temperature days, safety issues need to be valued."
Zhu Weigang said that at present, there are nearly 70 inspectors in the company's parks in the job. They are working on the request of "one hour of inspection and copying the table once every two hours". Once the problems are found, they need to be dealt with in time.
The reporter also learned from the Shaoxing Emergency Administration that, as a chemical city, Shaoxing has 125 hazardous chemical production enterprises. Under high temperature, these companies have established a safety inspection system to actively ensure production safety.
- END -
Dehua: The rain is sunny, and the heart "rescue" the ginger
Morning Post (Correspondent Li Hongtu Lai Yunping reporter Chen Xiaofen text/pictu...
Fujian Zhe'an: Repair the old house and check the hidden safety hazards
In the past few days, our county has further promoted the investigation and rectif...