In 10 days, they are put into 3 -seater substation at Hangzhou Power Supply Company to ensure safe electricity at high temperatures at high temperatures

Author:Hangzhou.com Time:2022.07.12

"Happy birthday to you, happy birthday ..." At 21:00 on July 9th, 110 kV Yun Valley in Sandun Town, Xihu District, Hangzhou, was put into operation smoothly. The room sounded. "Today is my 35th birthday, and it is also the birthday of Yunu's change. I think it is the most precious fate of the electric operator!" This is the number one in the start of the start of the startup of the Tianhu Power Supply Company of the State Grid Hangzhou Power Supply Company. For three substations, more than a dozen colleagues who participated in the production of the commissioning chorus blessing songs after the work. The sudden surprise and full ritual sense made Ye Haijun look a little embarrassed.

In July, Hangzhou opened the barbecue mode and continuously released high -temperature orange and red warnings. In order to ensure the safe consumption of the city at high temperature, the State Grid Hangzhou Power Supply Company is intensively drumped into 220 kV Yuqiao changes, 110 kV town, and the 110 kV Yun Valley transformer three -seater substation, adding 680 trillion mighty peace transformers Capacity is equivalent to adding two new Chun'an County power supply. The three -seater substation is adjacent to the country -level digital Yungu Life Demonstration Zone. Recently, it will be completed in the Alibaba East Data Center, West Lake University, and Cainiao Supply Chain. Timely power guarantee will provide sufficient momentum for the construction and development of the region.

The third substation launched within 10 days is the most densely launched in the State Grid Hangzhou Power Supply Company in the past ten years. "Examine.

Under the burning of the sun, the earth was baked and the dust was mixed with heat waves, but they could not stop their footsteps at all. Time, heavy tasks, and pressure on safety management and control, civil construction and equipment acceptance are carried out simultaneously. The temperature is nearly 40 degrees and the surface temperature is more than 50 degrees. There is no air -conditioning and fan in the unopened substation, and there is no windy on the stuffy. Ye Haijun and his colleagues switch rooms, control rooms, main variable rooms and other equipment rooms are often reversed. The substations are back and forth inside and outside the power station.

As early as 2 months ago, in order to ensure the change of 220 kV Yuqiao, 110 kV town, and 110 kV Yun Valley transformers, three substations can be put on time and smoothly. Running back and forth between three scenes has begun. From infrastructure acceptance, hidden danger rectification, PMS ledger to the preparation of transportation schedule, equipment acceptance, Sanyao core pair, from production auxiliary facilities and safety construction periods to the start -up operation, each link of the customs project.

"Yungu Ten 10 kV home line ground cars and homeline side -by -line electric monosters are unlocked", "110 kV town, No. 2 ground -used ground knife set, network door electromagnetic lock is not encouraged!", "Yuqiao becomes 35 35 When the two -segment parent cars are located in the working location, they do not close the bus sword car of the bus! "... The ten days of the startup operation, Ye Haijun departed at 6 o'clock every day, arrived at home at 9 pm, took off the hard hat, the hair was wet, and the hair was as wet. After washing, the clothes were covered with white salt.

During the acceptance and renewal process of the first round of the substation, Ye Haijun led a total of 405 hidden dangers with rich on -site experience and solid theoretical and technical level, and completed the rectification one by one.

"The successful completion of the three -seater substation is put into production. Whether it is safe, quality or construction, it is best to achieve the best!" Ye Haijun said, one of the birthday wishes made has been realized. There is also a wish. Ye Haijun hopes to keep power and safety during this year's peak summer.

In order to ensure the safety of the grid during the summer of this year, 165 people operating on duty at the State Grid Hangzhou Power Supply Company entered the 24 -hour "preparation status" of the peak summer, and updated the focus of operation and maintenance daily. The diversified means such as warm and charging detection conducts "whole body test" for substations, and "real -time follow -ups" are "real -time with the inspection robot, remote monitoring system, auxiliary control system, and drone.

- END -

Zhengzhou's newly added case of confirmed cases and 1 asymptomatic infection, the event trajectory was announced

About Zhengzhou's newly added case of new coronary pneumonia and 1 asymptomatic infectionOn July 11, 2022, at 21:00 on July 12th, a new case of new coronary pneumonia is added and 1 asymptomatic infec...

Guandu District Meteorological Observatory issued heavy rain blue warning [Class IV/general]

At 09:15 on June 9, 2022, the Meteorological Station of Guandu District issued a heavy rain blue warning signal: In the past 12 hours, the Airport Economic Zone has a long water airport, Baogui River,