10 new subway lines under construction in Guangzhou, 5 lines have exceeded half of the progress
Author:Golden sheep net Time:2022.07.10
Text/Drawing Yangcheng Evening News all media reporter Xu Zhentian
On July 10, the Guangzhou Metro informed 10 (sections) of the latest construction progress of the new rail transit line under construction. Among them, 5 lines were over half, and Line 11 was far ahead with 81%progress. As of the end of June 2022, the detailed construction progress of each line is as follows:
Progress map (drawing Xu Zhentian)
Line 3 Dongyan section (Panyu Plaza-Sea Piece): 73%of the civil engineering projects have been completed. Among the four stations, two have been capped, and the remaining two are carried out in civil construction; two of the four areas have been connected, and the remaining two and the entry and exit lines are undergoing civil construction. Guangzhou New Town Parking Lot is under construction.
East Yan section 5 (Wenchong-Huangpu Passenger Transport Port): 64%of the civil construction projects. Among the 6 stations on the entire line, 3 stations have been capped and started mechanical and electrical construction, and the remaining 3 of them are carried out in civil construction; two of the 6 areas have been connected, and the remaining 4 and the entry and exit are under construction; Shuanggang parking lot Construction of civil construction.
The second phase of Line 7 (University Town South-Northwest Water): 76%of the Civil Construction Project has been completed. Among the 11 stations, 5 were capped and started mechanical and electrical construction, and 6 of the civil construction were carried out; 6 of the 11 areas have been connected, and the remaining 5 and the entry and exit lines are undergoing civil construction. The Jiotang parking lot is carried out in civil construction.
Line 10 (Xiyi-Shipai Bridge): 47%of the Civil Construction Project has been completed. Among the 14 stations, 4 were capped, nine were carried out in civil construction, and the remaining 1 of the remaining 1 was prepared; 3 of the 14 sections had been connected, and 3 and the entry and exit section were carried out for civil construction. The construction of the vehicle section of the Guangsteel New Town is carried out.
Line 11 (Railway Station-Pazhou-Railway Station): A total of 81%of the civil engineering project was completed. Of the 32 stations, 2 have been opened, 14 have been capped, 15 are under construction, and 1 of the remaining one is prepared in the preliminary preparation. One of the 32 interval has been built and opened, 15 has been opened, and 14 of the civil construction is carried out. Construction, the remaining 2 are prepared before construction. The construction of the Chisha vehicle section and the entry and exit section is carried out for civil construction.
Line 12 (Yifenggang-University Town South): 45%of the civil engineering projects have been completed. Among the 25 stations, 6 are capped, 18 are carried out in civil construction, and 1 of the remaining 1 are prepared; 3 of the 24 areas are connected, and 11 of the civil construction construction is carried out. The remaining preparations are carried out. The section and entry and exit section of the head, the South parking lot of the university town and the entry and exit line for civil construction.
The second phase of Line 13 (Chaoyang-Fish Bead) has completed a total of 51%of the civil construction projects. Among the 23 stations, 5 are capped, 17 are planned for civil construction, and 1 stations are prepared for preliminary preparations. Among the 23 areas, the entry and exit lines of the 5 areas and the Phoenix parking lot have been connected. Preparation for preliminary preparation. Fish Parking Lot, Phoenix Parking Lot and Cover for civil construction.
The second phase of Line 14 (Jiahe Wanggang-Guangzhou Railway Station) has completed a total of 35%of the civil construction projects. Among the eight stations, the four main structures were capped, two were construction in civil construction, and the remaining two were prepared for preliminary preparations. Among the 8 sections, 2 were connected, 4 were carried out in civil construction, and the remaining 2 were preparations.
The rear section of Line 18 (村--Guangzhou East Station): The cumulative 10%of the civil engineering project is completed. One station is prepared for preliminary preparations, and the construction of civil construction in one section is carried out.
Line 22 (Chen Tougang-Fangcun): A total of 22%of the civil construction project was completed. Four stations are undergoing civil construction; one of the four sections is carried out in civil construction, and the remaining 3 are prepared for preliminary preparations.
- END -
"Municipal Supervisor Blue" on the "epidemic" line on the same boat to build a defense line
According to the current severe and complex epidemic situation and the needs of pr...
Guhu Street, Longchang City: Sorghum Branches have rushing in the autumn harvest
You see our sorghum is round and sloppy, this year's harvest must be good! Liu Zho...