There are new progress in the subway that pass through Huangpu!Add tunnel to
Author:Guangzhou Huangpu released Time:2022.06.13
The new week and new surprise
New subway line in front of the house
The construction progress bar is quickly loaded
1
Add tunnel to the second phase of Metro Line 13
Recently, the "CG Qingfeng No. 1" shield machine shoulder the "CG Qingfeng One" shield at the right line of Shield Tunnel of the Right -to -Phoenagraz between the 3rd phase of Metro Line 13 came out of the north end of the Phoenix Station, marking the smooth realization of the interval to achieve the smooth realization of the interval Double -line penetration.
At the same time, the rising shield tunnel from the rising sun to Qingfeng interval and the east extension of the east extension of the Metro Line 5 of the Metro Line No. 5 Shield Tunnel can also be fully connected.
up to now
Bleak
Phase II of Line 13
(Chaoyang-fish beads)
The second -phase engineering line of Line 13 is moving, starting from the rising sun, ending in the first phase of the engineering fish bead station. , Pearl River New City, International Financial City, Huangpu Lingang Business District and other key development areas.
✍ Latest progress
Cumulative 49%of civil engineering projects.
Among the 23 stations, 3 have been capped, 19 are construction for civil construction, and 1 stations are prepared in the early stage; in the 23 sections, the five areas and the Huiqian parking lot in and out of the field have been connected. Preparation for preliminary preparation.
Fish Parking Lot, Phoenix Parking Lot and Cover for civil construction.
2
The latest progress of the east extension section of Line 5 and the second phase of Line 7
Bleak
East extension of Line 5
(Wen Chong-Huangpu Passenger Transport)
The line starts at Wenchong Station on Line 5 and terminates at Huangpu Passenger Transport Port Station. The total length is about 9.76 kilometers. The maximum speed is 90 kilometers per hour.
✍ Latest progress
A total of 60%of the civil engineering project was completed.
Among the 6 stations on the entire line, three stations have been capped and started mechanical and electrical construction, and the remaining 3 of them are carried out in civil construction; two of the six areas have been connected and 4 are carried out in civil construction.
The entry and exit lines and Shuanggang parking lots are carried out for civil construction.
Bleak
Phase 2 of Line 7
(University Town South-Northwest Water)
The second phase of Line 7 starts at the South Station of the University Town and ended at the Northwest Railway Station. The total length of the line is 22 kilometers, all of which are underground lines. There are 11 stations of Shenjing, Changzhou, Hongshengsheng Sha, Yugui Wai, Dasha Dong, Ji Tang, Kaizhuang, Kofang, Shuixi, and Waternary West 11th stations in the second phase of the second phase. Among them It can be transferred to Suiwan -Shenzhen Intercity Pazhou branch, east extension section of Line 8, Line 13, Line 5, Line 19, Line 6, Twenty -1 Line, etc. The maximum running speed is 80 kilometers per hour.
✍ Latest progress
The cumulative civil engineering project was completed 73%.
Among the 11 stations, four have been capped and started mechanical and electrical construction, and 7 of them are carried out in civil construction; 3 of the 11 areas have been connected, and 8 are carried out in civil construction.
The Jiotang parking lot is carried out in civil construction.
Subway construction acceleration
The neighborhood life is happier
Forward+like
Together, I look forward to the 3 subway penetration as soon as possible!
Material Source 丨 Guangzhou Metro
Edit 丨 Yixiu
Review 丨 Yilong
Review 丨 Yini
Issuing 丨 Xu Qingyang
Produced 丨 Huangpu District Rong Media Center
Reprinted, please indicate 丨 Guangzhou Huangpu Posted
Point sharing
Point collection
Nap
Click to see
- END -
Jiangsu Province elected to attend the 20th National Congress of the Communist Party of China
On June 23, the Jiangsu Provincial Party Conference elected 71 representatives of ...
Shijiazhuang City releases the reporting channel for rectification of pension fraud
In order to resolutely implement the requirements of the central and provincial an...