Lucheng's placement house is capped 55 days in advance!This year's plan to complete more than 10,000 sets of relocation and resettlement ...

Author:Wenzhou News Network Time:2022.07.07

On the hot summer, the construction of the resettlement house was also "steaming." On July 6, with the pouring of the last meter concrete, the main body of the B-9-2 resettlement house in Yangyi Street in Lucheng District was fully concluded 55 days in advance, and since then entered the decoration stage. It is reported that the project will provide 885 sets of resettlement housing, and strive to debut in November this year. It will be completed in April next year and enter the completion acceptance stage.

The B-9-2 resettlement housing project is located in the cave bridge plot of Yangyi Street, with a total construction area of ​​162847.2 square meters. It consists of 9 high-rise housing and has a total investment of 1.213 billion yuan. The western transit road reconstruction project, the southwest high -speed, cave bridge construction and other projects have been relocated. Speed ​​up to both high standards and high quality, which is a regular action of the construction of Lucheng resettlement houses. The project construction adheres to the concept of "lean construction", focuses on humanization, ecology, digitalization, and align with the concepts of neighbors, health, low -carbon and other concepts. Infrastructure such as lawn and neighborhood activities will meet the people's longing for a better life and create a true project.

Since the start of construction, in the face of the current status of large engineering volume, tight time, and high attention, the project construction party China Railway Construction Group Wenzhou Construction Co., Ltd. has taken the goal of the total construction period, overcome the impact of epidemic, continuous rainfall and high temperature operations. Innovative technologies, combined processes and other measures to ensure that the project construction has changed every day, the progress of Zhou Zhou, and the results of the moon and the moon. In terms of process processing, the project tower crane implantation of visual monitoring system, strengthening process supervision. The main structure adopts prefabricated technologies such as PC structure, ALC prefabricated wall board, and the comprehensive pipeline layout adopts BIM technology. Process time to achieve quality improvement and efficiency. "We will continue to implement fine operations, work hard in safety, quality, construction details, and coordinated coordination, and strive to build projects into model engineering and boutique projects. At the peak of construction, more than 800 workers adhere to the progress of the post and the guarantee period to ensure that they are as soon as possible to ensure their early days. Realize the eager wishes of the residents' relocation. "Zhang Tianyou, the project manager, said.

During the construction, Yangyi Street recognized the contradiction between the demand gap in the construction of the resettlement house and the urgency of the residents to relocate and resettlement, and actively responded to the deployment of the reform model of the resettlement housing. "The project is built on behalf of the whole process of real estate enterprises. We play a role in supervision and coordination in the middle, and provide agreed management of quality and construction period to ensure the construction of high quality and stability of the project." The second half of the article in the village in the city, through the placement in advance, maximize digestion of vacant housing stocks, and prepare for the masses to realize the dream of settlement in advance.

Disassembling the old house, starting a new home, when to move into the ideal new house, related to the vital interests of the masses involved. The person in charge of the District Chengzhongcun Reconstruction Construction Center said that "the best placement of houses with the best location" is a solemn commitment made by Lucheng to the relocated people. It is planned to complete more than 10,000 sets of relocation and resettlement throughout the year. In addition, Lucheng plans to launch 11 resettlement commercial housing projects this year to build more than 5,100 sets of houses and houses and houses. Many people's livelihood landmarks, play the strongest sound of people's livelihood supplementing shortcomings.

- END -

The world's first!Open today!

Today (June 16)Hotan to Ruomao Railway(The following referred to as He Ruo Railway...

my country's successful launch high score 12 03 star

At 23:46 on June 27, 2022, Beijing time, my country used the Long March 4 Cross Ro...