Battle of the light and the wind and rain -National Net Huaihua Power Supply Company's flood resistance and electricity work documentary
Author:Red Net Huaihua Station Time:2022.07.07
"Fellow, you see that this air switch is already moist, and then continue to use short -circuit risks. Let me exchange for one." On July 3, Guonet Huaihua Power Supply Company Oriental Red Communist Service Team went deep into Tanjiachang, Chenxi County. Township, the villagers' family inspection table and switch are the villagers who are influenced by the flood.
Plug back to last month. "The 6 -hour rainfall reached 382.8 mm!" On June 19, a hundred -year -old heavy rain mountain flood attacked Chenxi County, affected by floods and mudslides, and in the severe disaster area, Xiuxi Town, Tanjiachang Township, and Shixi Township in the disaster area. The roads in some villages are not connected, and landscapes appear in the local area, causing multiple houses to be destroyed and damaged. The power supply line and equipment have been severely damaged, and more than 20,000 households are affected.
The "6.3" flood was superimposed, and the two consecutive rounds of disaster weather caused Chenxi County Power Grid to be tested unprecedentedly. In the face of the disaster, the party committee of the National Net Huaihua Power Supply Company accurately dispatched, coordinated command, and gathered the elite power to go to the front line.
Calling is here: Tongzhou John Jiqi
"Be sure to go all out to each other, and work together to win this tough battle to win the flood -resistant electricity!" On June 19, Guonet Huaihua Power Supply Company held a special meeting again. Rotal flood prevention work is re -deployed and re -arranged.
The flood situation is the command. After the flood, all employees established the idea of "one game of chess" to strengthen the awareness of the overall situation and responsibility. Comrade party members took the lead and played the role of vanguard modeling, and devoted themselves to the work of anti -flood relief and restoration of power supply.
State Grid Chenxi County Power Supply Company immediately launched an emergency plan, comprehensively entered the "wartime" state, launched a three -level warning of anti -severe rain and rain, held an emergency dispatch meeting, deployed flood -resistance and electricity and electricity. Power grid operation control and key equipment special patrol special protection.全体人员迅速展开分工协作,该公司领导班子分组下沉一线,督导现场应急抢修;安监、供指、配网24小时在岗值班,统筹协调应急、电网信息收集、现场决策指挥;物资、后勤、 Marketing and other departments coordinate together to clean up and allocate materials, implement protection needs, and visit service users.
"I am a party member, and I am more familiar with the routes there. Let me go!" Xiang Jie, the director of the Fire Horse Power Supply Station, once worked in Xiuxi Town, who was severely affected, and knew the local line operation. Later, he hurriedly called the leaders of Chenxi Company and asked him to form a rescue team to go to the front line.
"I applied to join the team!" As the personnel continued to invest, Chenxi Company quickly convened more than 260 people to form 7 rescue and disaster relief foreons. At the same time, more and more external support forces have come from all directions.
Yao Benjun, the leader of the Power Supply Company of Xinhuang County, received the call from the unit to support Chenxi. He couldn't care about the exhaustion of the day before the day before, and went straight to the front line without hesitation. There are more backbone forces from Xinhuang, Jingzhou, Channel, Mayang, Tong, Hongjiang City and other brothers' units from Xinhuang, Jingzhou, Channel, Mayang, Ji Tong, Hongjiang City and other brothers. Put the front to Chenxi Company, and the on -site scheduling solves the problem of guarantee.
Those who want to win up and down. Gathering and unity at all levels has won valuable time for rescue and disaster relief and restoration of power supply.
War can win: Iron shoulders carry the blame for light
"Everyone settled in the excavators, cranes and routes of their respective teams according to the arrangements just now!"
Since the flood, Pan Yuanhong has appeared at more than six o'clock in the morning every day, Pan Yuanhong has appeared in the Xiuxi Power Supply Center on the day of repair personnel and materials. This is the busiest moment of the day. After the departments set off, he was relieved, and then rushed to the repair point.
The flood caused the power supply of the 10 kV lines of Chenxi, 4 of which were responsible for daily operation and maintenance management by Xiuxi Power Supply Center. According to the arrangement of Chenxi Company, the important tasks of on -site coordinated personnel, vehicles, equipment materials and uploading were also undertaken. The Xiuxi Power Supply Center has also become a "distribution point" for post -disaster repair.
The traffic jams make the repair more difficult. Under normal circumstances, it takes an hour and a half from the farthest repair point from the power supply place to the farthest repair point, and on the road to the disaster area, every few hundred meters can be encountered in the area that washed by the landslides of the mountain. Hour. The hindrance of roads often causes large -scale operating vehicles to stagnate. In addition, the previous communication signals have not recovered. In the mountains, the rescue team that cannot contact the operating vehicle must be passed back and forth by people.
"The government and the village committee know that we are going to repair the power, and they are supported by coordination." After emergency operations, the interrupted road was snatched, and the repair vehicles finally went deep into the hinterland of the affected area. The principle of retreating into the electricity and sending electricity, a lantern also lit up day and night with the tireless manner of the repair personnel.
Among this group of rescue teams, Dai Jun, the Power Supply Institute of Tanwan, may be the one who wants to be re -power as soon as possible.
When the flood occurred, his mother and her four -year -old daughter were in the home of Tanjiachang Township. The flood not only destroyed the two houses, but also destroyed the local publicity sequence tower. For a while, he could not contact his family.
"It's particularly anxious, but this is a established fact. It is better to repair as soon as possible and send electricity to the hometown earlier!" Holding the belief of re -powering as soon as possible, he took the initiative to apply for joining the rescue team, buried in the bottom of his heart, and delivered the time to millions of households to transport thousands of households to transportation to millions of households. bright. "10 kV Tanjiachang Township Line successfully delivered electricity!" "10 kV Wujiawan Township Line successfully delivered electricity!" All the people overcome the difficulties and reported frequent reports. With communication and power recovery, Dai Jun also knew that his family was safe. Message.
At 20:49 on June 28th, with the turn of the router after the circuit breaker No. 121 of the Xiuxi Houkou Shixi Township Line, the route is transferred to the router, and the Maojiaping branch line is transferred. Rebuild the "battle" comprehensive.
Action must be fruit: the mission of chopping thorns practice
On June 22, a orange -red helicopter slowly landed in the Square Square of Xiuxi Town, Chenxi County after completing the monitoring task of this round of inspection. And vegetables and fruits.
Due to the unknown disaster situation of part of the distribution lines in the hardest hit area, the line operation is unclear, which brings great difficulties to emergency response. After striving by the National Net Huaihua Power Supply Company, they successfully applied for a helicopter to a helicopter for the air tour in the disaster area, and the disaster collected in the air was synchronized to the relevant technical personnel of the repair team for analysis.
"The helicopter aircraft is not limited by regional, and it can also be equipped with personnel, materials, and equipment for transportation operations." Using the advantages of the helicopter aircraft operation, the State Grid Chenxi County Power Supply Company actively cooperate with the county party committee, and actively cooperate with the county party committee. The county government asked for entrustment to carry the rescue supplies to the disaster area.
"The situation of a pregnant woman nearby is not very stable." Luo Yiling, who was frightened by the flood, was frightened by the flood, and her 7 -month pregnancy was frequent.
After the supplies are uninstalled, the space out of the plane can be carried. With the assistance of the local women's federation, the aircraft that completed the supplies immediately carried the couple and transferred to a safe place.
There are both "heroes" from the sky, as well as more mortals who come out. Knowing that Xiuxi Town and Tanjiachang Township was completely interrupted due to the landslide and the main roads caused by the collapse. It was like a "island" situation. , 80 bags of rice, etc., rushed to the disaster area to send a love area.
After passing the stagnant water, turning into the muddy mountain road, the road became more and more bumpy, and the hearts of the players also followed seven and eight: "The road is so difficult to walk, what can be delivered to the supplies?" Not long, the chaotic stone completely blocked the road, the vehicle It was completely unable to pass, and all the team members immediately decided to get off and transport the materials to their destinations.
"Everyone is working hard to take out the spirit of our State Grid people!" Although all the way up, the team members encouraged each other to cheer each other to cheer each other. After more than 2 hours of trampping, the service team finally arrived in the disaster area. The supplies are safely sent to the masses.
"Thank you very much. Not only did he repair the line day and night, he also sent us supplies!" Holding the emergency food in his hand, Shishanguang villagers in Shishan Township said grateful to the service team.
Along with the supplies to the disaster area, there is also a warm service from the National Nets. The flood is infused, so that many houses are immersed in water for a long time, bringing users a safety hazard. After the water was retreated, the team members took the toolkit, a household went to the interview, inspected the hidden dangers of electricity in villagers' home, and obliged to replace the tables and lines to provide accurate services for the people in the disaster area.
Don't be afraid of wind and rain, the more difficult the more difficult. As of 18 o'clock on July 1, the National Net Huaihua Power Supply Company has invested more than 5,000 construction forces, more than 970 vehicles, more than 190 large machinery, and 288 platforms and 21975 users have fully recovered. In this flood -resistance and electricity war, the majority of cadres and employees have been tested with their determination, unyielding spirit and actual actions, and practiced the original intention of serving the people with blood, giving up the powerful power to protect power supply.
- END -
Foxconn (Weihai) Science and Technology Industrial Park Project is enabled and put into production
These trains will resume the run!You can directly reach Beijing and Shanghai
1. Standing on July 8th, Jilin to Shanghai K518/5 resumed operations; on July 10th, the stations were started, and Shanghai to Jilin K516/7 times resumed the operation.吉林至上海K518/5次:吉林8:07始发,沿...