Yingzhou Qingji Yanji is at the beginning of the prototype of the extension of Yanhe Road on action
Author:Yanji Propaganda Time:2022.07.06
In the midsummer, the construction of the Yanji City project was also launched like tea. After two months of intense construction, the extension of Yanhe Road extended project has begun to emerge.
Photo by Jin Hongshi at the construction site
Yanhe Road extension project starts from Xinmin North Street in the east, and in the west to Yanchuan North Street. The road is 2.4 kilometers in length. It intersects with Democratic Street and Minchang Street along the road. The lane contains 4 lanes and 2 lanes of the motor vehicle, and the width of the sidewalks on both sides is 4 meters. Tree pools are set on the sidewalk.
Photo by Jin Hongshi at the construction site
According to Ma Yan, deputy station director of the Quality Supervision Station of Yanji City Construction Project, as a key project of urban construction, the Yanhe Road extension project is a new road to optimize the construction of the western urban road network and relieve transportation. Construction content includes road base engineering, retaining wall engineering, rainwater pipeline engineering, sewage pipeline engineering, street light engineering, facade engineering, green tree pool, and small bridge along the line.
Photo by Jin Hongshi at the construction site
At present, all the construction content of the retaining wall project and the culvert project has been completed; the road base project and the rainwater pipeline project have completed 70%of the corresponding total; the 46 prefabricated beams and 21 drilling piles of the bridge engineering have been completed. Construction of inheritance and pier pillars.
Frequent rainfall during the flood season has affected the construction, and the project department has formulated a scientific and reasonable construction plan. Ma Yan said that the Yanhe Road Extension Project plans to complete the construction of the remaining road base projects and rainwater pipeline projects in mid -to -late July, the construction of bridge projects at the end of July, and the construction of water stability and surface layer project in August.
- END -
Sun Yat -sen University Report: The investigation has been launched!
On the evening of July 2nd, a network post questioned on the Internet questioning ...
23 Provincial Civil Servants' joint examination issued Huatu Education on the 9th: 5.6%expansion, competition ratio 36 to 1
On July 9, the 2022 Civil Servant's Provincial Examination Test was officially launched by the epidemic. A total of 23 provinces and autonomous regions in the country participated in the joint examina...