Guangdong Hydropower's first land wind power project in 2022 successfully connected

Author:Yangcheng.com Time:2022.07.05

(Yang Yang Zhao Jiao) At 11:08 on June 29th, with the official charging of the fifty wind power project of the 13th room wind farm of Guangdong Hydropower Hami, the fans were officially charged. The 50MW wind power project of Hami Thirteen Fangfeng Electric Farm has been connected smoothly, and the remaining units will be connected one after another. This project is the first single -machine wind power project to connect to Guangdong Hydropower in 2022. It is also the period of the Xinjiang Energy Company to grasp the development opportunity period and energy transformation window period of Xinjiang. 20 clean energy projects.

The project is located about 55 kilometers in Qijiaojing Town, Yizhou District, Xinjiang, with a total installed capacity of 50MW. The 8 typhoon uses the second largest power wind turbine in the country. The volume is 140 million kilowatt -hours, which can save 41,700 tons of coal a year and 114,000 tons of carbon dioxide reduction, which is of great significance to optimize the energy structure and promote energy conservation and emission reduction in Hami region. As one of the important wind outlets in the country, the famous "Baili Wind Area" in Xinjiang and one of the main battlefields of clean energy investment and development -Hami 13 Fangfeng District is located in the Lanxin Railway Hami to Laoshan Square. The crown of the whole country and the second in the country. Although the wind resources are enriched, the climate is very harsh, the indoor temperature of the room in the midsummer can reach more than 50 ° C, and there are countless weather and dust weather. Level, but the fearless and hard -working, hard -working and hard work of the party members of Yueshui Power Xinjiang Energy Company lead the front -line employees to fight day and night. The first company to complete the grid -connected power generation task in the 1 million kilowatt wind power project. Party members and cadres have taken the heavy responsibility and lasted 121 days to transform the former "blocking wind" into a new "green energy source" for economic development in Hami, Xinjiang.

Fans crane

Since its official construction on March 1, 2022, it has faced bad factors such as harsh construction conditions and difficulty in transportation of most components. , Li Kaijun, the person in charge of the Hami region, adheres to the front line, carefully organizes the construction of the project, strives to coordinate the procedures, all personnel are united and cooperative, overcome difficulties, and strive to show the responsibility and responsibility of state -owned enterprises. Realize grid -connected power generation.

Early site selection: 2 tires of 2 tires under 10 hours

Wang Dongbiao is working

In the early days of the project construction, Li Kaijun, Wang Dongbiao, and Li Lin, who were freezing and trembling, began to embark on the road of site selection and seek a "home" for 8 typhoon machines. It only takes an hour to choose the micro -location of the normal predictive fan, and the thirteen houses under the rugged road, they just ran for more than ten hours in the inside inside of Gobi Beach to be determined, and they were tired again. Hungry again, they finally looked forward to "going home", but the car "couldn't hold it anymore". Two tires and twice were supplemented. Until 4 am, they finally reached the temporary project department and pushed it. At the moment of opening the door, it was like pushing "hope".

The road to construction: "It's not easy here"

Zhong Guoqing, deputy chief engineer of Xinjiang Energy Company, is guiding the work

For Zhong Guoqing, the deputy chief engineer of Xinjiang Energy Company who participated in many construction projects, investment projects and development and construction, Hami Thirteen House projects are really not easy! During the construction, Zhong Guoqing discovered that the supply of tower tower was insufficient and the problem of transportation was very tricky. He immediately decided to go straight to the tower barrel to supervise the quality of monitoring. After a few days, the tower was delivered as scheduled. However, the severe weather has also affected the lifting work. He calmly responded and deployed it secretly. With the joint efforts of all participants, using the joint efforts of all participants, using each section of wind and air stitching period, under the premise of ensuring safety, under the premise of ensuring safety To solve the problem of hanging, write "not simple" with "simple".

Early connection: "Xinjiang Yue Hydropower People" under the night of sleeping

"Xinjiang Yue Hydropower People", which is still debugging at 4 am

Urban situations are often difficult to predict. On the eve of the connection, the provincial and ground -to -point parties have emerged in some situations, affecting the advancement of the grid -connected work. At this time, the "Xinjiang Yue Hydropower" from various power stations to the Hami project to investigate all equipment overnight. Cao Tong, who had rich experience, did not slack down, and communicated closely with the ground adjustment, and finally completed the work. But just after being excited, there was a problem with the optical fiber on the opposite side of 220. He continued to investigate overnight without complaints. Everyone worked until 4 am to complete the joint work and ensured the smooth connection of the project.

The smooth grid of the large -capacity fan of the 13 -room single -body fans of Yue Hydropower Hami will play a pioneering role in emerging fields such as the large -scale development of Yue Hydropower and the application of multi -scenario applications such as the application of land wind power resources and energy storage power stations. Yue Hydropower helps Xinjiang's clean energy market operation and maintenance technology changes lays a solid foundation.

- END -

Bei Chen District Leadership to Enterprise Research Service

On June 24th, Feng Weihua, secretary of the Beichen District Party Committee, led ...

Provincial Agricultural Inspection Center came to Jiuquan City to conduct a second livestock and poultry product quality and safety routine sampling

Promote the healthy development of the grass and livestock industryProvincial Agricultural Inspection Center came to Jiuquan City to conduct a second livestock and poultry product quality and safety r