First -line visible 丨 Construction lifting growth road network extending the Quartet -Urumqi infrastructure construction fast horse plus whip
Author:Tianshan.com Time:2022.07.05
Reporter Zhang Dongmei Intern Wang Mengru
The reconstruction and expansion project of Urumqi Airport has been comprehensively promoted, and the main body of the main body of the comprehensive pipe gallery of the eastward field elevated roads in the east is emerging. , The blue sky tower hangs, the construction staff is hard -working, the building grows, and the road network extends the Quartet.
Since the beginning of this year, Urumqi has continuously strengthened infrastructure construction, has made up shortcomings with project construction, further releases investment potential, and promotes high -quality economic development.
On July 2nd, the reporter saw at the construction site of the reconstruction and expansion project of Urumqi Airport that the new terminal in front of them had begun to take shape. Construction work is progressing in an orderly manner.
On July 2nd, the construction of Urumqi Airport's reconstruction and expansion project is being advanced in an orderly manner. Reporter Zhang Dongmei Photo
In the processing area on the west side of the original host building, the welding worker Gao Jianhui welded the cut square steel into different shapes, and several workers not far away were undergoing keel processing on the surface. In the material area, the forklift that shuttles the back and forth to transfer the material to the designated area.
Entering a new terminal, the construction of flooring, indoor ceilings, and new material installation of walls are being carried out here. On the third floor of the terminal, the material worker Feng Jianguang was busy. After processing the colored steel plate into a pressure -type steel plate, he stacked the steel plate neatly aside. Ma Jiuhua, a welder standing on the crawler car, is welding on the lambout part of the terminal. "This is what we practice. It is proud to be able to participate in such a large project!" Ma Jiuhua said.
On July 2nd, workers were welding operations at the construction site of the Urumqi Airport. Reporter Zhang Dongmei Photo
Zhao Yufeng, the production manager of the reconstruction and expansion project of the China Construction Third Bureau, introduced that the subsequent corona project construction and honeycomb aluminum plate installation are one of the difficulties of the project. "Before the construction of the cornice project, we used computer software to establish a three -dimensional three -dimensional model. The on -site professional measurement tools were adopted by the whole station instrument. After multiple reviews and measurement, we can carry out construction operations to ensure the installation accuracy." We are driving hard and go all out to ensure the construction of the terminal.
As a key project of the autonomous region, the construction project of North Railway Road (Batang Highway-Airport Expressway), Urumqi City, has a total length of 11.1 kilometers. Today, both sides of the north station of the east -west station have been surrounded by iron, and construction vehicles such as excavators, loaders, and transport vehicles shuttled back and forth.
On July 2nd, the workers were reinforcing the template at the construction project site at Beizhou Road (Batang Highway-Airport Expressway) construction project at Urumqi. Reporter Zhang Dongmei Photo
At the fourth bid section, Wu Bigang and more than ten workers were reinforcing the main templates of the pipe gallery, and the steel bars of the pipe gallery were also carried out simultaneously. In the steel processing plant next to each other, after the crane was uninstalled to the fixed area, more than a dozen workers made different styles and models of steel bars through equipment, and some workers welded the reinforced reinforcement to reinforced cages.
At the site of the first bid section, the northern half of the road was underway. After the workers Leng Jiaying and Yang Taishan sorted the block size on the road surface, a road pressure machine was compacted, and the flat floor machine will The road surface is flat, and the scene is orderly.
On July 2nd, the workers were operating in the steel processing plant of the construction project of North Railway Road (Batang Highway-Airport Expressway) construction project in Urumqi. Reporter Zhang Dongmei Photo
"The main body of the pipe gallery has been completed about 6 kilometers, and the road pavement project has begun construction." Yan Xiang, director of the engineering department of the Xinxiang Construction Bayi Project Investment Management Co., Ltd., Urumqi, said that at the end of this year, the Bayang Highway to the Uui Expressway The 6 -kilometer North Station Highway will be opened to traffic. The remaining sections are expected to open to traffic in October next year.
"Once the entire line is opened, the North Station Road will change from 4 lanes to two -way 8 lanes. West of Urumqi will have an extra traffic road." Yan Xiang said.
The construction site on the ground is promoted in an orderly manner, and the underground pipe gallery project is also being constructed simultaneously.
The construction of the Dongjuan Elevated Road Comprehensive Pipe Corridor Project, which is responsible for the construction of Urumqi Underground Comprehensive Pipeline Investment Management Co., Ltd., is also promoting in an orderly manner.
On July 2nd, the construction of the Edach Road Comprehensive Pipe Corridor Project of Dongjinchang Pass in Urumqi is under construction. Reporter Zhang Dongmei Photo
On the same day, at the construction site from Baiyuan Road to Anning Qu section, more than 10 template workers after lunch breaks began to set up template branches of the main framework of the pipe gallery. At the bottom of the pit at about 12 meters deep, some workers operated operations. Equipment perform pile operations.
Underground comprehensive pipe gallery, known as the "underground lifeline" to ensure urban operation. The reporter saw at the scene that the main structure of the pipe gallery about 200 meters was completed here. Among the three cabins, the comprehensive cabin in the middle is relatively large, and the electric cabin and gas compartment on both sides are relatively small. The bottom plate, top plate and exterior wall of some pipe galleries have been poured. At this time, Xia Yuwen and the workers stood on the 2.5 -meter -high operating platform and were tie the steel bars of the gas compartment and the middle wall of the comprehensive cabin.
On July 2nd, the construction site of the ergrout roads of Urumqi City, the construction site of the Elevated Road Comprehensive Pipe Corridor project, workers operated on the operating platform. Reporter Zhang Dongmei Photo
- END -
B -end product manager: How to design product architecture for complex digital projects
Edit Introduction: In the environment of digital transformation, more and more com...
The word "hot" in Guangdong in the next three days!The biggest "Super Moon" this year will appear tomorrow night
Currently, southern ChinaI have experienced this yearThe longest high temperature ...