Hangkou Meridian, 20 minutes!
Author:Changjiang Daily Time:2022.07.01
Recently, many netizens
Consultation on the message board of Wuhan City
Connecting Hanyang, Wuchang, Hankou multiple areas
Left Bank Avenue Expressway Project
The latest construction progress
The relevant departments replied one by one
On March 10, the long river section of the left bank (Wanjia Hunan Road -Xiajun Mountain) in the intense construction. Reporter Li Ziyun Photo
Wuhan Development Zone replied that after verifying the left -bank avenue project from the north and the south to Hannan Xingqi Road, the project is divided into 4 sections:
1. Chaoskou section (Third Ring Road -Wanjia Hunan Road): The project starts on May 18, 2022, and the contract period is 900 days. It is expected to be completed on November 224, 2024.
2. Changhe section (Wanjia Hunan Road -Xiajun Mountain): The project starts on February 8, 2021, and the contract period is 720 days. It is expected to be completed on September 7, 2023.
3. Smart Ecological City Section (Chuanjiangchi Road -Fenglin VI): The project is currently ending. It is expected to be completed in July this year.
4. Dajun Mountain Avenue (Little Junshan -Chuanjiang Chi Road, Fenglin VI Road -Xingqi Road): At present, the project is currently in the early stage of construction. In the future, the project construction work will be promoted in an orderly manner to strive to start and complete the traffic as soon as possible.
It is reported that the three -ring line of the left bank avenue from the north, Dengnan Port District in the south, and a length of about 48 kilometers throughout the line. It is the traffic arteries on the integrated development zone of the Yangtze River left bank of the Wuhan Economic Development Zone. After Dongfeng Avenue and Jiangcheng Avenue, the Wuhan Economic Development Zone leads to the third main road to the main city. The important shot in the shooting, the south expansion section of the main axis of the Yangtze River.
According to the plan, the left -bank avenue section is implemented in 4 road sections in installments, and one formation is taken in accordance with the fast road standards. The road standard is designed according to no less than two -way 6 lanes. Underground comprehensive pipe gallery. Among them, after the completion of the third ring road from the left bank to the Grand Army, the drive from the Wuhan Economic Development District Junshan New City and the central city of Hankou will be shortened from 40 minutes to 20 minutes.
Changjiang Daily Da Wuhan client product.
For more exciting content, please download the "Da Wuhan" client in the major application markets.
- END -
A magnitude 4.4 earthquake sources in Weining County, Bijie City, Guizhou 12 kilometers
The Chinese Earthquake Network officially measured: June 20th at 06:40, a magnitud...
Zou Ping: For a while, greedy stretched thieves to "hold the sheep" and was detained
Qilu.com · Lightning News July 11th. On July 6, the Jiaoqiao Police Station of th...