Yi -Bo -Wu -Phoenix II Return 750 KV transmission and transmission project Starting wire show
Author:Tianshan.com Time:2022.06.30
The first wire show
Tianshan News (Reporter Chen Qiangqi reported) On June 28th, a set of wires slowly extended to the distant iron tower about 20 kilometers away from Jinghe County, driven by the traction machine. This is Yili -Bozhou- The first wire of the Wusu -Phoenix II 750 kV transmission and transmission project marks the last process of the project's entry into the main construction.
Yili -Bozhou -Wusu -Phoenix II Return 750 kV transmission and transmission project is a key project of the "Fourteenth Five -Year Plan" of the autonomous region, a key project of the autonomous region in 2022. Essence The project starts from the 750 kV Yili transformation station, and stops at the Phoenix 750 kV power station. The line passes through 8 counties including Nilek County and Jinghe County. The length is about 421 kilometers. Construction was started on the 20th. It is expected to be fully opened in October 2022, and it is planned to be completed and put into operation in 2023. After being put into operation, it will effectively improve the power delivery ability of Ili Kazakh Autonomous Prefecture to Wuchang Load Center.
The geographical environment across the entire line is complicated, not only across railways, highways, Monhara Forest Park, Dushanzi Grand Canyon, and Manas River, but also span more than 200 electric lines. The 80 -kilometer line is located in a mountainous area of 800 meters to 2500 meters above sea level. The terrain conditions of the mountainous areas are complicated, and it is difficult to carry out wire exhibition operations.
State Grid Xinjiang Electric Power Co., Ltd. uses three -dimensional aerial image information technology to select tension fields and traction fields with relatively flat terrain to ensure the smooth development of wire exhibitions. It also ensures material transportation by setting up ropeway in the mountains.
At present, the project's entire line of the tower has been completed by 85%, and all iron tower formation is expected to be completed at the end of August.
- END -
Construction waste cannot be dumped at will!Some people have been fined: fine+responsible for repair
■ Comparison before and after repair. Recently, the Municipal Resources ...
Luoyang Yichuan Shangyuan Village: Natural gas, the countryside becomes more beautiful
Top News · Henan Business Daily reporter Fu Shoupeng Correspondent Ge Gaoyuan Liu...