"One place and two batches" provoke disputes!Multiple departments in Yuelu District played balls, and one million projects could not operate!

Author:Hotline for the people Time:2022.06.27

Complaints from enterprises: A piece of land was approved to two companies to cause disputes, causing more than 12 million yuan to disappear the field cannot be operated.

Mr. Lu is the head of Hunan Quanyufeng Construction Engineering Co., Ltd.. On December 18, 2020, the company and the wholly -owned enterprise of the Lianhua Town Government in Yuelu District, Changsha City, Changsha Lotus Construction Investment Development Co., Ltd. signed the "Cloud Gravate Degree Land Lifting Project Cooperation Agreement".

According to the relevant provisions of the agreement, Changsha Lotus Construction Investment Development Co., Ltd. was commissioned by the Lianhua Town Government to contracted a waste -cooked field in Yungai Village in Lianhua Town to Hunan Quanyufeng Construction Engineering Co., Ltd. Essence

On December 18, 2020, the cooperation agreement signed by the two parties signed by the two parties. Interviewee confidence

Later, their company submitted an application for approval for the project approval of the residue soil to consolidate the dregs. "The departments participating in the approval include the Yuelu District Branch of the Natural Resources and Planning Bureau of Changsha City, the Yuelu District Agricultural and Rural Bureau, the Yuelu Branch of the Changsha Ecological and Environment Bureau, the Yuelu District Emergency Management Bureau, the Yuelu District Urban Management Bureau, the Yuelu District City Rong Environmental Sanitation Maintenance Center slag Earth Affairs Management Section. On the approval form, these departments have stamped their chapters, and the deputy head of the urban management work also signed. "

The registration form is set up in Yuelu district residue. Interviewee confidence

On April 27, 2021, under the Department of Standard Management of the Municipal Environmental Sanitation Maintenance Center in Yuelu District, the dregs of the residue disappearing field setting up formalities were issued, allowing Hunan Quanyufeng Construction Engineering Co., Ltd. By April 27, 2023, the dregs can be eliminated according to the relevant management requirements of residue disposal.

The notice of setting up the formalities in Yuelu District Slag Substitute. Interviewee confidence

Changsha residue soil disappearing public announcement bar. Reporter photo

Lotus Cloud Cover Slag Earth Toll Public Publicity Sign. Reporter photo

The completion of the slag car washing groove has been built. Reporter photo

However, in May 2021, when the company was preparing to formally operate the slag soil, it was suspended by the dregs management department of the city capacity and environmental sanitation maintenance center of Yuelu District. "They said that they could not have a slag soil, and this land has long been planned, which is used to use construction waste resources. I look back to understand this plan. planning"."

Subsequently, the reporter also checked the plan. It was compiled by the Changsha Natural Resources and Planning Bureau in 2020, and was approved by the Changsha Municipal Government. According to the relevant provisions of this plan, the site selection of the construction waste disposal base of Yuelu District is 2.1 kilometers south of Quanshui Road, and within 500 meters east of Huangqiao Avenue, it is actually Hunan Quanyufeng Construction Engineering Co., Ltd. The venue of the market.

The reporter also inquired on the official website of the People's Government of Yuelu District that on August 13, 2020, commissioned by the Yuelu District Government, the Yuelu District Urban Management Bureau made public bidding The project land is provided by the district government. The abandoned pit and surrounding areas are tentatively scheduled to be at the junction of Yungai Village and Bachelor Street Xuehua Village in Lianhua Town (have been included in the "Special Plan for Building Waste Governance in Changsha City". August 2020, Hunan, Hunan Yunzhong Recycling Technology Co., Ltd. will win the bidding, which will build construction waste treatment plants in the planned area.

The results of the bids of the construction waste resources of the construction waste resources of Yuelu District were publicized. Page screenshot

The company believes that: multiple departments in Yuelu District are negligent in work, and should be responsible for planning for planning and approval.

Due to the overlapping planning site selection and the planning approval time of the planning of the construction waste treatment plant, the residue disappearance project that was repeatedly planned and approved was therefore not operated.

In this regard, Mr. Lu believes: "The Lianhua Town Government and the relevant approval departments of Yuelu District have lost their jobs. Contract. The second is the unit in charge of approval. Since this land has been planned, it should not be approved on the same land on the same land. Therefore, this responsibility is not my operating party. It should be caused by the Lianhua Town Government and the examination and approval departments of Yuelu District. They should take responsibility for this. "The slag dumping field project has been put on hold for more than a year, and the company has difficulty in operating the company.

The location of the Yun Gai slag soil is located. Reporter photo

However, what made Mr. Lu was chilling that the relevant government departments in Yuelu District were reluctant to take responsibility for the wrong approval of this project. So far, the plan has not been solved, which has caused a serious impact on the company's operations. "I invested a total of 12.6 million yuan in this project. I have all handed the copy of these payment vouchers to the Lianhua Town Government, and I also submitted a written report to solve this problem as soon as possible. So far, there is no reply. No department organizes me or our company to have a coordination meeting to see how to deal with this. At present, the approval party does not care, and the Lianhua Town government does not care, let me wait, and it cannot be dragged. If it is not handled, the company's capital chain will be fracture."

The report submitted by Hunan Quanyufeng Construction Engineering Co., Ltd. on the request to properly handle the "Cloud Grav Slag Sub -Laboratory Cooperation Agreement" as soon as possible. Interviewee confidence

Yuelu District Municipal Rong Environment Sanitation Maintenance Center, Changsha Natural Resources and Planning Bureau Yuelu District Branch, Yuelu District Urban Management Bureau, Lianhua Town Government kick the ball with each other

Subsequently, the reporter accompanied Mr. Lu to first find the scum management department of the Yuelu District City Rongsheng Environmental Sanitation Maintenance Center who stopped this project. A staff member of the surname Du said that it was indeed because the site selection of the two projects was overlapping. In the operation of the residue soil, the planning department and the urban management department should be responsible for this incident.

"Since this place has long been planned to engage in construction waste treatment plants, your district and rules and regulations should take the first level. You said that this place can not have a slag to the ground, and other departments behind it will not exist. Since the signing of the seal. Since the District Urban Management Bureau has already carried out the bidding for the use of franchise projects for construction waste resources, it is also a leading unit for approval of this slag to disappear. Question. Our Sanitation Center is responsible for post -approval supervision, that is, your dregs disappear the ground to enter the soil and report it here. "

Later, the reporter and Mr. Lu found Su Yulin, deputy director of the Yuelu District Branch of the Natural Resources and Planning Bureau of Changsha City. He said that the location of the two projects overlap was caused by information asymmetric. "((Building garbage treatment plant) is not a point in our district, it is the point of the city in the city. Then Hunan Yunzhong Renewal Technology Co., Ltd. is planned with the clothing point in the city, saying how you are in the same land again After criticizing a slag to eliminate the market, we did not know this in advance. This is essentially the problem of information asymmetry. For example, you know the information of this cloth point, and the person who is responsible for approval is not known. Further verification, it has caused the planning site overlap. "

Moreover, Su Yulin also believes that the Urban Management Bureau of Yuelu District is not strict with the site selection of the dregs. "You said that the District's Institute of Ziqi has been wrong. Does the District Urban Management Bureau know where to distribute a bit. They are the leading department and the industry authority. You should also know if you want to engage in construction waste treatment plants. "

Yu Xinyue, deputy director of the Urban Management Bureau of Yuelu District, did not deny the approval of the urban management department, but he believed that the planning department should bear the main responsibility. "We have made mistakes in the approval of the approval. We don't know where the specific location of the construction waste treatment plant is. The first word, so the biggest responsibility lies in the District assets and regulations. "

But how to solve this problem, Yu Xinyue suggested: "The bell must be tied to the bell, you are a project talked to the Lianhua Town Government, you have to find the Lotus Town Government to give a solution. If you can't get it, you need to compensate. After all, the company already has such a large investment, and give it a statement. "

Later, the reporter and Mr. came to the Lianhua Town Government again and found Li Jiancheng, a member of the town party committee and the chairman of the National People's Congress responsible for finance and audit work. He said: "The deputy head of the urban management work has clearly told us that this slag has not done it, and the next step is to talk about compensation. The deputy mayor let us communicate with your company first, and it is probably necessary How much is compensated. "

However, Ji Wenbin, Secretary of the Party Committee of Lianhua Town, said: "This problem is useless to find us, and we cannot determine how to compensate you. What we can do at present is to continue to report to the district government."

Corporate question: The relevant departments of the Yuelu District Government are not responsible and inaction

The location of the Yungai Degree Land Linking Field Project is currently not operated and shelved for more than a year. Reporter photo

Due to the errors of the planning and approval of multiple government departments in Yuelu District, it has been put on hold for more than a year for more than 12 million yuan of slag, but the relevant government departments are unwilling to take responsibility for this matter, and they are unwilling to take the initiative to take the initiative to take the initiative to take the initiative to take the initiative to take the initiativeTo solve this problem.Especially after the project has clearly been canceled, the issue of how the government compensation is still delayed.This disappointed Mr. Lu."They are too irresponsible, that is, pushing, procrastination, and kicking the ball. No one wants to take responsibility. As a government functional department, it is really difficult to understand." Finally, reporters and Mr. Lu alsoThis issue is reflected to the Yuelu District Government Office, and the district government is requested to coordinate and resolve it.For the follow -up progress of this matter, "The Hotline for the Min" will continue to focus on.

Reporter: Ocean


- END -

Zhengyu high -speed rail tickets are on sale!Take a car for 2 hours and 11 minutes to go to the Shennongjian to avoid the summer heat

The Yangtze River Daily Da Wuhan Client June 17th (Reporter Chen Yongquan) On the ...

Xinjiang Fire Department carried out a "scenic line" for fire safety inspections to build a safety inspection of scenic spots

Tianshan News (Reporter Guo Ling reported) Our scenic spot is newly opened. As lon...