Report from the front line of Taixin Economic Construction ▏ Taixin Avenue 2nd standard road bridge pile foundation construction volume was completed by 85%
Author:Shanxi Painting News Xinzhou R Time:2022.06.26
Xinzhou Daily News (Zhang Zhiyuan) The sun is like fire, and the heat wave strikes people. In the past few days, the city has ushered in high temperature and hot weather, the ground temperature has risen, and the hot weather is unbearable. The builders of the second bidding section of the Taixin Avenue, which were undertaken by the China Construction Third Bureau Group Co., Ltd., fought high temperature, fighting heat, grabbing work, and rushing progress. Actions contribute to the project construction.
On the morning of June 24th, the reporter saw at the construction site of multiple operations on the second bid project of the Taixin Avenue. The mechanical banging on the construction site was rang, the engineering vehicle shuttled back and forth, the construction staff was scorching the sun, sweating like rain, and fully promoted the spirit of continuous combat, paved the way to pave the way, and paved the way. , Digging and bridging, various construction operations have been steadily advanced. At the construction site of key control projects such as the second -standard section across the Erguang Guangzhou Bridge, the workers kept busy at the moment of the heat wave. The project construction "accelerates".
The construction period is command, and the quality is more critical. "We strictly control the quality during the construction process, and find a balance point between seizing the construction period and ensuring the quality of the quality. More than 300 people operate at the same time." Cheng Long, a technician of the technicians who is undergoing the construction of the workers. In order to ensure the quality of construction, the project department chose an excellent team with many years of construction experience to ensure the professionalism of the construction team. In each process, there are professional technicians to supervise. Grasp. It is understood that Taixin Avenue is the north extension of Yangxing Avenue in Taiyuan City. After completion, it can directly reach Xinzhou City from Huangzhai Village, Huangzhai Town, Yangqu County, Taiyuan City. Taixin Avenue (Xinzhou City-Shilingguan section) project general contracting EPC second bid section, 5.117 kilometers throughout the line, builds 1 interoperability bridge, 3 main bridge, 6 horizontal cross-line bridges, 20 culverts, 4 channels, 4 channels 4 Taoism, 1.477 million cubic meters of excavation and 569,400 cubic meters of filled meters.
Up to now, the construction of the road bridge pile foundation of the second bidding section of the Taixin Avenue project has been completed, of which 82.5%of the pile foundation of the upper and secondary Guangzhou high -speed bridge has been completed; the construction of the bridge inheritance has been completed by 24.5%; %. 34.9%of the road -based earth and stone construction was completed. The construction of Handong has been completed by 30.9%. After the opening of the Taixin Avenue, the traffic pressure from Xinzhou to Taiyuan section will be greatly alleviated by the G55 (Erguang Expressway), and the distance between Taiyuan and Xinzhou, expanding the urban circle of the two cities, and promoting the economic development of the two cities. It has great practical significance and far -reaching historical significance for promoting the integration of Xinzhou south into the Taiyuan Metropolitan Circle, accelerating the construction of open development, and improving the quality of the people.
Source: Xinzhou Daily
Edit: Zhang Weiping
Responsible editor: Fan Jingyu
Produced: Fan Wenzhen
All rights reserved, please indicate the source
Submit mailbox: [email protected]
News hotline: 18803508818
13903508888
18135050587
- END -
Hurry up and refund the money!The end of this month
According to the announcement of the State Administration of TaxationFrom March 1,...
2022 Lingnan Intellectual Property Litigation Conference was successfully held in Guangzhou Intellec
On June 1, 2022, the 2022 Lingnan Intellectual Property Litigation Conference was ...