Approval!Putian will build 9 new roads
Author:Straits Herald Putian News Time:2022.06.24
good news!
Putian will build 9 new roads
↓↓
Putian City Yixi Construction Development Co., Ltd.:
Your Division "Putian City Yixi Construction Development Co., Ltd. on the application for approval and approval of the urban road network project and feasibility study report of the Chengdong District Road, the Yixi District" and related attachments are received. After research, principles agree to build the project, and the relevant matters are approved as follows:
1. Project Name: Langxi District Chengdong Division Road Network
(Project code: 2112-350304-04-01-771164)
2. Construction address: Gongchen Street, Licheng District
3. Construction scale and main content: 13.7816 hectares of project planning land, 9 new urban roads. in:
①西洪北街(八二一北街至下店路):城市次干路;规划道路红线宽度为30米;道路北起八二一北街(现状)、交叉南郊路、南郊北路、 Northern Road, the south to Xiadian Road, with a total length of 1266.926 meters; the road is two -way four -lane, with a design speed of 30 kilometers per hour.
② Zhenhai North Street (Bayer North Street to Xiadian Road): Urban secondary road; planning road red line width is 24 meters; from the north of the road, 821 North Street (status quo), crossing Xi Geng Er Road, Xiging San San San Road, south to Xiadian Road, a total length of 708.024 meters; the road is two -way four -lane, with a design speed of 30 kilometers per hour.
③ Nanjiao Road (Yanshou North Street to Liyuan Road): Urban secondary road; planning road red line width is 24 meters; Yanshou North Street (current status) from the west Garden Road, a total of 977.501 meters; the road is two -way four -lane, with a design speed of 30 kilometers per hour.
④ Haifeng North Street (South Suburban North Road to Xiadian Road): Urban branch road; planning road red line width is 24 meters; the north of the road from the north of the north of the north, crossing the southern suburbs, north all road, south to Xiadian Road, total length of 813.468 meters, a total length of 813.468 meters ; The road is a two -way four -lane, the design speed is 20 kilometers per hour.
⑤ South Suburban North Road (Yanshou North Street to Xirong North Street): Urban branch road; planned road red line width is 18 meters; Yanshou North Street (current status) west of roads, crossing Haifeng North Street, east to Xichong North Street The total length is 646.56 meters; the road is two -way two lanes with a design speed of 20 kilometers per hour.
⑥ North Road (Haifeng North Street to Sanjiao Third Street): Urban branch road; planning road red line width is 18 meters; the west of the road from Haifeng North Street, crossing Xirong North Street, south to the third street of the south, 581.315 Mi; roads are two -way lanes with a design speed of 20 kilometers per hour.
八 Xi Gengyi Street (821 North Street to Xiadian Road): Urban branch road; planning road red line width is 16 meters; the north of the road, 821 North Street (status quo), crossing Xi Geng Er Road, Xi Geng San Three Road, south to Xiadian Road, with a total length of 578.732 meters; the road is two -way two lanes with a design speed of 20 kilometers per hour.
⑧ Xi Geng Second Road (Xiging 1st Street to Zhen Haibei Street): Urban branch road; planning road red line width is 12 meters; the west of the road west of Xi Gengyi Street, north to Zhenhai North Street, with a total length of 223.657 meters. The lane, the design speed is 20 kilometers per hour.
Xixi Geng 3rd Road (Bayer North Street to Zhen Haibei Street): urban branch road; planning road red line width is 12 meters; the west of the road, 821 North Street (status quo), crossing Xi Gengyi Street, south to Zhenhai North Street, with a total length of 406.063 meters; the road is two -way two lanes with a design speed of 20 kilometers per hour.
The construction content of this project mainly includes roadbed pavement engineering, road landscape greening engineering, municipal comprehensive pipeline project, street lighting project, transportation facilities engineering, bridge culvert project, etc.
4. Total investment and funding sources: The total investment of the project is 123,388,100 yuan, of which: the construction cost of Jian'an is 303.216 million yuan, the project construction costs are 839.216 million yuan, and the basic reserve fee is 91.3947 million yuan. Source of funds: In accordance with the Minutes of the Putian Municipal People's Government's special meeting [2019] No. 33, it is raised.
Fifth, construction period: 24 months.
6. Social stability risk assessment: The project has carried out social stability risk assessment in accordance with relevant regulations, and was reviewed and approved by Gongchen Street Office. The overall risk level of the project is low risk. Please strictly implement project risk prevention and resolution measures, and effectively safeguard the vital interests and social stability of the masses.
7. Engineering bidding: shall be implemented in accordance with the bidding and bidding law and relevant regulations.
8. Energy -saving requirements: You should build energy -saving technologies, processes and equipment in accordance with relevant energy saving standards and standardized construction, strengthen energy -saving management, and continuously improve the energy efficiency level of the project.
9. Others: Please conscientiously implement measures such as safety production, environmental protection, and soil and water conservation in accordance with relevant national regulations.
Based on this batch, please hurry up the institutions with the corresponding qualifications to carry out survey and design work, prepare preliminary design of the project, and report the initial design of the project in accordance with regulations. For relevant procedures of other departments, please handle it in accordance with relevant laws and regulations.
Development and Reform Bureau of Licheng District, Putian City
June 2022
- END -
Dazhou: Let the Provincial Party Congress spirit enter the mind
Sino -US relations are at the key crossroads!China ’s latest statement releases a clear signal
On the afternoon of June 15, President Xi Jinping called with Russian President Pu...