The industrial steam engineering project of Tieli Economic Development Zone enters the equipment installation and commissioning stage
Author:Tieli Rong Media Time:2022.06.23
The Industrial Steam Engineering of Tieli Economic Development Zone is one of the current key projects in our city. After the project is completed, it will provide steam supply services for companies such as Longtai Food Co., Ltd., Heizhen Edible Musk Planting Co., Ltd., and Sunflower Pharmaceutical Group. Reduce the production cost of the enterprise. At present, the main building construction of the project and the laying of the external steam pipeline have been basically completed, and the installation and commissioning of internal equipment is underway.
On June 21, the reporter saw at the construction site of the industrial steam engineering project of the Tieli Economic Development Zone that the excavator outside the venue was in a hurry to carry out the level of the venue. Work and provide guarantee for subsequent construction. In the main building, the main equipment in steam production links such as the dust workshop and boiler workshop has been installed, and the workers are carrying out the welding of the pipeline.
It is understood that the total investment in the industrial steam project of Tieli Economic Development Zone is 45.3 million yuan. In order to ensure the rapid advancement of the project, the current construction party has invested 2 excavators, 1 crane, 2 forklifts, and 70 on -site construction workers. Steady operations under the premise of ensuring safety and quality. After the project is put into production, 10 tons of steam will be produced per hour, which can fully meet the steam supply of food and surrounding foods and pharmaceutical manufacturers.
Cheng Shaojun, an on -site construction manager: "Our external installation and interior decoration are nearing completion. It is expected that the debugging will begin at the end of August.
- END -
How many are there in the intersection of the intersection in the center of Kunming?Official reply
A few days ago, some netizens reported to the Kunming 12345 Mayor's hotline throu...
Bama County Meteorological ORC releases lightning orange early warning signals [level/severe]
At 07:55 on June 10, 2022, the Bama County Meteorological Orange was lifted.