good news!IntersectionQinhuangdao's road is finally open →
Author:Shijiazhuang Daily client Time:2022.06.23
"After the opening of this road, not only is it convenient for everyone to travel, it has widened people's hearts. Our business is better than before. The number of guests is significantly increased. It is a good thing that is clearly set." Mr. Zhou, a merchant near the street, cleaned the sanitation at the entrance, and smiled at Yaoyuan Street just opened in front of him, praising the great thing that the Municipal Engineering Construction Service Center was a private thing.
The construction project (now Yaoyuan Street) of Bridge Dongli Planning Branch was completed in June 2017. However, at the connection with the West Gang Road intersection, due to the influence of the pumping station and the opening and closing of the opening and closing. "". As a result, residents in nearby communities such as Hua Yaocheng and Tang Heming built in the direction of West Port Road must bypass Heping Street and Friendship Road to bring great inconvenience to citizens.
△ Before the opening of Yaoyuan Street
△ After the opening of Yaoyuan Street
After learning about the situation, the mayor Ding Wei paid great attention and instructed the relevant departments of the city and the Harbor District to take it as a key project of the 20th Minsheng Practical Road this year. Plan, coordinate and solve the bottleneck constraints encountered in the process of demolition and new construction. The leaders of the Municipal Housing and Urban Construction Bureau have visited the construction site several times for supervision and inspection. After the project was launched, the Municipal Municipal Engineering Construction Service Center was responsible for the relocation and implementation of road engineering. After the joint efforts of the participating parties, the strong support of the Harbor District Municipal Facilities Management Center, the Urban Management Bureau of Harbor District, the Harbor District Garden Center, and the Municipal Electric Power Corporation will be fully cooperated. Completed as scheduled.
△ Yaoyuan Street after opening
The power relocation project of the opening and closing office of Xigang Road completed the renewal main structure on May 15 this year, and began to install the equipment. On June 1, 2, and 4th, the 30 lines of the original opening and closing office were cut and sent The electricity is completed. After the entire line was delivered on the afternoon of the 4th, all the equipment from the original opening and closing office was removed at 12pm. At 6 pm on the 5th, the house of the original opening and closing office and the sewage pumping station was demolished. On the 6th, the road slotted, and the water stability, asphalt, the sidewalk and the standard line were completed on the 12th.
△ Yaoyuan Street construction site
△ Yaoyuan Street construction site
"The entire project starts from West Port Road in the west, and the east to the original 3#pump station, open and closing office, with a total length of 30 meters, the road red line is 20 meters wide. Among them, the mixed lane is 12 meters wide, asphalt structure, and the sidewalk is 8 meters (4*2 ) Width. At the same time, the new supporting rainwater, street lights, greening, communication and other municipal facilities have been officially opened to traffic on June 12. "Chen Juming, the engineering department of the Municipal Engineering Construction Service Center, introduced that this is the city's open roads and solve the masses to solve the masses The people's livelihood engineering projects reflected in the hotspot and difficulties are of great significance for improving the function of urban road networks, solving the difficulty of travel, and facilitating the people's travel, and alleviating traffic pressure.
△ Migration of opening and closing
△ Migration of opening and closing
It is understood that Yaoyuan Street has a large underground pipeline and complicated, involving the underground, ground pipelines and facilities of more than 10 property units including rainwater, sewage, heat, and gas. conduct. In order to solve the difficulties of construction, the Municipal Municipal Engineering Construction Service Center has repeatedly organized a pipeline coordination meeting to formulate a relocation plan, and requires the construction unit to reasonably arrange the process of interspersed procedures to ensure that the project is progressing smoothly and completed on time.
Source: Qinhuangdao Evening News
- END -
The people's happy life is the greatest human rights 丨 Guizhou language skills "double training": happy life "say" out
Xinhua News Agency, Guiyang, June 18th: Guizhou language skills double training: h...
From 14:00 on the 20th to 17:00!The highest temperature in most parts of Haikou City will rise to above 37 ° C
Commercial Daily All Media News (Coconut Network/Altitude mobile phone reporter Ch...