Shijiazhuang, Hebei: Metro Line 1 Phase II project is advanced at full speed
Author:Great Wall Stone Time:2022.09.28
Great Wall Network · Jiyun Client, September 28 (Reporter Kang Yihan Correspondent Tian Zhangmeng) This morning, the construction site of the second phase of Shijiazhuang Metro Line 1 was busy. The structure is excavated at full speed at an underground at 18 meters from the ground. The total length of the tunnel in this area is about 2279 meters. As of now, the left -line tunnel has been excavated 801 (about 961 meters long), and the right line has been excavated by 521 ring (about 625 meters).
Construction workers laid track in the tunnel. Photo by Kang Yihan, a reporter from Great Wall Network · Jiyun Client
The northern part of the second phase of Shijiazhuang Metro Line 1 is Fuzawa Station (excluding) to Toyo Station and Nanniu Parking Lot. It started construction in December 2021. The current projects under construction mainly include Dongshangze Station to Toyo Station, Toyo Station, Toyo Station to Nanniu parking lot, and Nanniu parking lot. Connected to open to traffic. Yu Jinbo, head of Shield of Shijiazhuang Metro Project Department of China Railway Eighteen Bureau, introduced that the second phase of Shijiazhuang Metro Line 1 of the second phase of the northern section of the construction of the second phase of the construction has entered the construction acceleration period. Stop, the left and right dual -line can dig more than 10 rings per day.
Construction workers laid track in the tunnel. Photo by Kang Yihan, a reporter from Great Wall Network · Jiyun Client
The construction staff is loading the prefabricated tube film to the tunnel. Photo by Kang Yihan, a reporter from Great Wall Network · Jiyun Client
In addition, the windy wells from Dongshangze Station to Toyo Station have completed the concrete structure of the deep -founded pit side; Toyo Station has completed the construction of enclosure piles and crown beams, and a total of 95,000 cubic meters of earth excavation has been completed. Construction of negative two -layer side wall concrete and reinforced bars.
- END -
The first phase of Zhengzhou Metro Line 14 resume operation
On August 26, a reporter from the Dahe News Daily · Yu Video learned from Zhengzh...
Beijing needs to be rented today and needs to be signed for contracts
According to@September 1 news, today, the first local regulations in the country to regulate housing rental Beijing Housing Rental Regulations was officially implemented. Rental housing also require