Dazhou City Second Water source Bayhe takes the annual target task in advance

Author:Dazhou released Time:2022.09.26

Dazhou City Second Water source Bayhe water collection project

The total number of contracts has been completed by more than 70%,

Complete annual target tasks in advance.

As a major livelihood project in Dazhou City and the preliminary project of "Drimination of Water into Bamboo", Dazhou City Second Water Source Basuan Water Revision Project includes two parts: water lifting pump station and diversion line. The three groups of Bayi River in the Bay Town Instains River, the scale of the Bazi River is designed with a water supply scale of 200,000 m³/day. The main urban area and the urban area of ​​Dazhu County have been developed by water resources restrictions.

Dazhou City Second Water source Basu River Water Revision Project has 4 tunnels: Da Gao Lian, Liu Jiayan, Wangjiaping, and Xianpo Ridge, including Gardenba, Berlingou, Caojiagou, and the front -end pipeline, Xianpo Ridge out of the front -end pipeline, Xianpo Ridge out of the outlet The water mouth diversion into the library and the dark canal, which is about 16 kilometers in length, of which 15.336 kilometers are tunnel, accounting for about 96%of the total line.

At the same time, the front -end pipeline will play the role of the Papahe River to take the water outlet to the large tongs. The back -end dark canal and Ming canal will play the role of the exit of the Xianpo Ridge tunnel into the warehouse, and the hear groove will play the penetration role of the tunnel and the tunnel in the valley.

On the morning of September 22, the reporter walked into the construction site of the three groups of pump rooms in the four groups of Gaogao Tunnels in the west side of the Shixiazi Reservoir, the Berlingou, and the inverted Hongcun Village. The pump room is a semi -underground structure. The main project is close to the end. The end -end of the water diversion line has been poured, and the water diversion tunnel project is stepping up construction, and the hetermonary project is stepping up the construction.

According to the person in charge of the construction unit project, at present, the Dazhou City Second Water source Basuan Papa River has completed more than 70%of the total contract project, and the annual target tasks have been completed in advance.

Among them, the pump 1#pump house has been capped, and the pumping room is about to be sealed. 85%of the excavation, 80%of the pipeline installation, and 80%of the pipeline packages have been completed;

Four drain tunnels have been excavated and the initial support of about 10,770 meters has been completed;

The foundation, pier pillars, and arranging construction of Yuanba, Berlin grooves, pier columns, and arranges have been basically completed.

The exit of the Xianpo Ridge Tunnel has been completed into the reservoir.

The person in charge of the project of the Municipal Water Affairs Group stated that in order to benefit the people in Dazheng as soon as possible and solve the difficulty of drinking water in Dazhu County as soon as possible, the company implemented the general requirements of "going all the way to fight for the economy and construction", and implemented the linked chart operation, reverse construction period, and tackling tackling. Difficulty, round -round homework, strive to sprint annual goals and tasks. At the same time, the "Drimination of Water into Bamboo" project has started construction, and various tasks are fully promoted in an orderly manner in an orderly manner. (Li Chunxue)

- END -

Landscape Links Revitalize the "Cultural Scripture"

Liu Mingzhi, Liu RuihuaWalking around, there are culture. The Zhuanghu Troupe come...

The 7th "Creative Jining" cultural product design and the first "Confucius Cultural Tourism Cup" hand -made contest ended