90 days running out of acceleration!Car Valley Power Battery Head Enterprise Dedicated substation realizes "electricity"

Author:Changjiang Daily Time:2022.09.25

The Yangtze River Daily Da Wuhan Client September 25th. On September 25, the 110 kV Special substation of AVIC Lithium Power in the China Central Enterprise Secondary Enterprise Second Airlines was successfully delivered at one time, and the entire line achieved "electricity". From the construction to the "Dentong", the project team only completed the efficiency of 90 days, and ran out of the municipal infrastructure acceleration.

AVIC's dedicated substation for lithium power has been realized. Reporter Gong Ping Photo

On the 25th, a reporter from the Yangtze River Daily saw in the Wuhan Economic Development Zone AVIC Lithium Electric Special Varling Station project that with various electronic devices that constantly flickered, the substation will operate normally. In the future The new energy vehicle sector of "Car Valley" develops rapidly.

Three months ago, when the project started construction, the various difficulties faced doubled the pressure of the project department.

"Underground projects like this, involving the" stirring "of various pipelines, if it is construction in the central urban area, it takes at least one and a half years; and the time for us is only 3 months. 'Dormation' problem. "Li Ming, the person in charge of the project.

The reporter learned that the first standard section of the China Communications Second Aviation Bureau was 9.6 kilometers in length, which is the most complicated bid section across the board. There are Metro Line 16 that is operating.

"At the most complicated intersection of Tongjiang Four Road, in order not to affect the pipelines of various roads, we used the" Yu Gong "method to artificially excavate. It took two weeks to complete the 20 -meter -long construction section. Equal ownership units simultaneously "stare" at the scene, and dare not have a little bit of tiger. "Zhifeng, the project production manager, said.

Construction in Wuhan for the first time, a large horizontal orientation drill was used for the first time. Correspondence

When crossing the Ma Yinghe River, which is nearly 300 meters wide, the project department used a non -excavated horizontal directional diamonds weighing 600 tons of non -drilling diamonds in Wuhan. Destroyed surface vegetation, which only affects the water environment and saves one month.

At the same time, the project department prepares a special construction plan in advance, refine and decompose the construction process and operation points, organize management personnel to conduct in -depth technical guidance and safety intercourse, strengthen standard management, strict process control, seize the golden period of construction, ensure the construction of the project construction Promoting orderly, realizing the entire power through the entire line during the planned period.

Last year, AVIC Lithium Power, a power battery head enterprise with a total investment of 10 billion yuan, settled in China Car Valley. And application fields such as energy storage markets. The successful power delivery laid a solid foundation for the successful production of this key project. (Changjiang Daily reporter Gong Ping correspondent Zhang Xiaolin Liu Xiyan)

[Edit: Deng La Xiu]

For more exciting content, please download the "Da Wuhan" client in the major application markets.

- END -

Chengdu Jinjiang District, Chenghua District: Bar, Tea House and other public places suspended business

The announcement of the office of the New Guan Guanye Pneumonia Epidemic Institute of Jinjiang District, Chengdu, Chengdu, and the business of public places for public places such as suspension of bar

Zaozhuang Mountain Pavilion develops summer greening and maintenance, dressed as a beautiful city

Qilu.com · Lightning News July 13th. Summer, various green seedlings enter the rapid growth stage, which is also the key time season for garden greening. In order to prevent early prevention and ear