Tianfu Avenue Meishan Section: Strive for the opening of traffic at the end of this month

Author:Published by Sichuan Time:2022.09.22

The Meishan section of Tianfu Avenue is a road that Meishan people are particularly concerned. The width of its road base is 80 meters and the two -way 12 lanes. Driving and running will be a kind of enjoyment! After it is opened to traffic, the time from Meishan to Chengdu Tianfu Plaza can save nearly half an hour.

Today, what is the road that is full of expectations? When can I open to traffic?

On September 21, the reporter learned that the Meishan section of Tianfu Avenue had been repaired to the East New District, and successfully merged with Yidong Avenue, and was undergoing the final hundreds of meters of pavement. Up to now, 99%of the Mengyan section of Tianfu Avenue has been laid, and the affiliated projects have been completed. The street lights and greening are still in intense construction, and strive to have traffic conditions at the end of this month.

At the intersection of the Meishan section of Tianfu Avenue and Jianpu High Speed, large -scale machinery such as road press and excavators is stepping up the operation and striving to grab the last 300 -meter node project. Some of the completion of the road sections appear, 80 meters of roadbed, two -way 12 lanes, straight lanes, and towering street lights are listed on both sides. The continuous green mountains snuggle will be a kind of enjoyment on the road.

Tianfu Avenue is connected to Chengdu Center and Tianfu New District. The development of radiation, eyebrows, and capital cities is not only a transportation road, but also a large economic and industrial channel. Among them, the Meishan section is an important part of Tianfu Avenue extends south.

The road project of Meishan section of Tianfu Avenue starts from Tianfu New District Shi Gao Town. The total length of the route is about 17.7 kilometers, the width of the road base is 80 meters, the two -way 12 lanes, the main lane design is 80 kilometers per hour, and the auxiliary road design speed is 40 kilometers per hour.

After the project was completed, Meishan people went to Chengdu to eat hot pot and shopping, and the time and journey will be greatly shortened. The journey from Meishan to Chengdu Tianfu Square is shortened by about 15 kilometers than before, and it can save nearly half an hour in time. At the same time, the people of Meishan went to Heilong Beach and Xinglong Lake to travel and sightseeing in the future, which are very convenient and fast.

Relying on Tianfu Avenue, Meishan is accelerating the creation of the Tianfu Avenue Science and Technology Corridor, and a coordinated innovation center of Meishan. At present, 57 companies in Meishan City have carried out cooperation in industry -university -research and research cooperation with universities such as Sichuan University, Electronic Science and Technology University, and organized 11 demonstration projects for the transfer of major scientific and technological achievements in Chengmei cooperation to comprehensively integrate into the Chengyu Science and Technology Innovation Center and the West (Chengdu) Science. The construction of the city, a community of innovation communities in Demei.

- END -

The Lanshan District Administrative Examination and Approval Service Bureau carried out the theme activities of "Remembering History and Cherish Peace"

In order to thoroughly implement the work deployment of the construction of the 3+1 theoretical armed system, and solidly promote the effectiveness of learning theory, understanding thoughts, seein

"Black Pearl" on the yellow land

"Data-version =" 0 "data-vwidth =" 1920 "data-vHeight =" 1080 "transcoding ...