Dalian upgrade and transformation 17 main and secondary roads
Author:Peninsula Morning Post Time:2022.09.22
17 road upgrades and transformation projects
A total of 497,800 square meters of maintenance lanes for maintenance
The total area of the sidewalk is 327,600 square meters, and the border stone is 64,800 Yanmi
This year will complete the maintenance of 8 roads
Morning News (Peninsula Morning News, 39 -degree Video Reporter Li Shesheng) On September 21, the reporter learned from the municipal center that based on the foundation of people's livelihood and unified deployment of the city's defense finger, this year's road reconstruction and expansion project has started on September 12.
This year, in accordance with the overall deployment of one -year plan and two years, the municipal center organized the implementation of 17 road upgrades such as liberation roads and Anshan Road. 64,800 meters of square meters and border stones. Among them, 8 roads such as Anshan Road, Southwest Road, and Yellow River Street will be completed this year. The total area of the car roads is 162,100 square meters, the total area of the sidewalk is 158,500 square meters, and the border stone is 23,500 meters. Based on the completion of the people's livelihood project, the pre -construction of drainage pipelines in liberation road maintenance will also be carried out simultaneously.
Since the establishment of the municipal center in 2018, the municipal government investment project has only arranged a large road repair project in 2019, with a total investment of 76 million yuan to use the road to overhaul. In 2020 and 2021, the road repair plan was not received for two consecutive years, which led to the current overall quality of the city's municipal roads declined. In addition, the excavation project's disturbance of road bases, and road disease damage increased. The intact rate of the main and secondary roads in the four districts of the city reached 79.95%. This year, it received a planned investment of 320 million yuan in the municipal finance and transformed 1 congestion road section. Reform 16 main roads such as Jiefang Road and Anshan Road. The road maintenance project of the municipal center has always been followed by "supplementing shortcomings, benefiting people's livelihood, excellent services, and promoting innovation" to reduce the impact on the surrounding areas.
Aiming at the flip -leakage soil and water stabilization gravel layer roads that are prone to produce dust during construction, the geomolutile cloth is strictly used for lids to effectively suppress the dust. Sprinkling vehicles track spraying operations in a timely manner. During the pavement health, duty personnel are equipped with duty personnel. During the non -peak period, it is guaranteed to reduce the dust and reduce the dust. Strictly control the noise pollution at the construction site. The first is to strengthen the operation and management of large -scale machinery and equipment that is prone to noise at the construction site, and build a chaotic cross -construction according to the requirements of the operation. The second is to arrange the operation time as much as possible during the day. Third, for some special road sections, the traffic construction cannot be closed during the day. Try to arrange the work that is easy to generate noise in the middle of the night, and at the same time reduce the production of artificial noise.
Considering that the maintenance is the main and secondary roads, and the main task of carrying urban traffic operation, most construction choices are carried out at night. In order to ensure that the people's livelihood project must be completed this year, the municipal traffic police detachment and other related units are fully cooperated, and they are adopted. Avoid the peak traffic peak in the morning and evening, and closed construction measures in the middle of the day and night.
■ Related link 8 road construction basic information
① Anshan Road (Northeast Road ~ Yangtze River Road), the road is 1889 meters in length, the car roads are restructured as a whole, and new sand throwing brick trails and polished granite edge stones are built. ② Southwest Road (Sha District Court ~ Xishan Street), the road is 1283 meters in length. ③ Huanghe Street (Northeast Road ~ Beijing Street), with a total length of 1045 meters. The car roads are restructured as a whole. ④ Xinsheng Road (Xiangzhou Road ~ Golden Shield Road), the road is 1655 meters in length, the car roads are restructured as a whole, the new square brick trail and polished granite edge stone. ⑤ Taiyuan Street (May 1st ~ Gorky Road), the road is 1175 meters in length, the car roads are restructured as a whole, and new sand throwing brick trails and glittering granite edge stones are built. ⑥ Bayi Road (Jiefang Road ~ Changchun Road), the road is 1123 meters long, the trail is damaged as a whole, and the new sand throwing brick trail and the polished granite edge stone.沙 Donglian Road Bridge (Shahekou Railway Station ~ North Station), the road is 11267 meters in length, and the road under the bridge is damaged as a whole. The total area of the new square brick trail is 60,935 square meters. Local new sawnuts are 7,300 meters. ⑧ Harbor Street (Yucai Street ~ Two Seven Plaza), the road is 240 meters long, the car roads are restructured as a whole, and the new sand throwing brick trails and local newly -made grinding granite border stones are built.
- END -
Henan Zhumadian: osmanthus is full of fragrance in the city
Recently, the autumn wind was refreshing, and many roads, squares, gardens, and co...
Suizhou City Carrys out the theme of science popularization of earthquake prevention and disaster reduction themes
Suizhou Daily (all -media reporter Chen Qiaoling) On July 26, the city launched th...