The road of Weicheng District is opened to traffic at the end of the month!
Author:Weicheng Rong Media Time:2022.09.22
As a key project that improves the quality of the city and dressed up in the face of beautiful cities, Dongfeng West Street Reverse Project has reached the end.On September 19th, on the construction section of Dongfeng West Street, Weicheng District, large -scale mechanical horsepower was fully opened and was laying asphalt at the bottom of the layer.
Dongfeng West Street's Revelation Project started in late February this year.This summer, Weifang's frequent precipitation has affected the construction progress.At present, the intersections such as Sanlizhuang Road and Anshun Road are closed.Under the supervision of the competent authority, the construction party went all out to rush to the work period and strive to open to traffic as soon as possible.
It is understood that the underlying asphalt paving is currently underway. In the later period, it will also be paved asphalt to improve the transportation facilities. It is expected that the project will be completed at the end of September to achieve the entire online traffic.
Dongfeng West Street's renovation project starts from Changsong Road in the west, and east of Yong'an Road.The original cement concrete pavement was severely damaged and affected citizens' travel.After the project is completed and opened to traffic, the comfort and safety of citizens will be fully improved.
- END -
Tongjiang County: Before the festival, "diagnose the pulse" to protect the lights of Wanjia
A phase 36.7 ℃, B phase 38.4 ℃, C phase 37.9 ℃. On September 8th, in the 10 kV ...
thrilling!Men's soap -made card toilet Lower sewer 4 hours
Recently, a man's right arm of Xuzhou accidentally stuck in the toilet and entered...