New Era of Endering New Journey | The construction rate of 99.3% of the key projects run out of "Weihai speed"
Author:Guan Weihai Time:2022.09.21
In order to thoroughly implement the decision -making deployment of "investment promotion and project construction years", since this year, the city has made unprecedented motivation to promote the construction of the project. Although the impact of the epidemic on the way, the construction of key projects still shows the start of landing. Fast and good investment in construction.
The Weihai Guangtai emergency rescue guarantee equipment production base project in Lingang District is a major provincial project this year, with a total investment of 1.8 billion yuan. In the first phase, it requires a one -time one -time single -body plant to complete more than 90,000 square meters. This project has been different from the beginning.
Zhang Jinglin, the manager of the project of Guangtai emergency rescue guarantee equipment production base: "You see this drainage ditch here, this spring is said to be heavy rain, so we can advance in advance, nearly 600 meters of drainage ditch, until June, until June, we will not be in June. After the construction, the facts prove that it also plays an important role. "
The terrain of the Guangtai Emergency Rescue Project is high and low, and the soil is sticky. However, because the project party predicted in advance, the drainage ditch was built. This year's rainy season did not affect the construction period. When many projects stopped because of the epidemic, the Guangtai project site was so hot.
The deputy director of the engineering construction center of Weihai Guangtai Air Port Equipment Co., Ltd. initially made: "We use the piano work method to accurately each step to each time, every week, every day. The work plan of the row is implemented. "
There is a plan for everything, and there are rules step by step. On the office wall of the project manager Zhang Jinglin, in addition to the annual plan, monthly progress, and weekly deployment of the project, there are two thick construction logs on the table. Nearly a year until now, the project is progressing, the staffing of the personnel, and the completion of Zhang Jinglin.
Zhang Jinglin, the manager of the project of Guangtai emergency rescue guarantee equipment production base: "You see our welding workshop steel columns now, all these six rows of steel columns are not stood up, now it has been installed, it can be over three days, it can be over three days. Or two days. "
Take one step, look at three steps, and seek five steps. Now, the first eight factories basic projects in the first phase of the Guangtai Emergency Rescue Project have been completed, and the second phase is about to start.
The deputy director of the engineering construction center of Weihai Guangtai Airport Co., Ltd. initially levies: "After the completion of this project, the annual production of various types of fire trucks and firefighting vehicles is about 2,000 units, and the output value may be about 3 billion yuan. The second phase of our fist product is the drone series. This year, I will start to start the land. "
A new project is a new economic growth pole. At the beginning of the year, Weihai revolved around 6 major sections including scientific and technological innovation, industry, urban construction, rural revitalization, marine industry, infrastructure and public services, and determined 810 municipal key projects. After the project was determined, the Municipal Development and Reform Commission first clarified the person in charge of each project, and formed a "1+6" city -level key project promotion system that was both responsible and closely cooperated. In the city, the city continued to roll up key projects. On February 16, May 7, and September 9, respectively, three key projects started construction activities. 804 key projects continued to start startup, setting off the city's key projects in the city The boom of construction.
The Hon Hai Metro Tunnel, which is located in Zhangcun Town, Huancui District, is manufactured by the reinforcement of carbon fiber compound cavity. It started construction in April this year. In less than 5 months, 4 monomer buildings have been capped.
Hon Hai Metro Tunnel Reinforcement Reinforcement Carbon Fiber compound compound component manufacturing project A representative Zhang Hang: "From the beginning to the project to prepare all the data, the government is also a green light, such as the node of the project, involving the acceptance of the pile foundation and the foundation of the foundation. In the acceptance of the sub -department, the competent authority can never drag until the next day. "
"Followed by the project", as large as the key node acceptance, as small as fragmented trivial affairs, the person in charge of the city, district, and towns and streets "three -level linkage", promoted a "small unit" to enter the project site from the office, and solve the project fully to solve the project. A series of issues such as land, funds, and procedures during the construction process have become the norm in the project promotion process. In order to avoid repeated scheduling between different departments, the municipal development and reform departments will include all the projects into the municipal project management service platform in accordance with the principle of "a network management, a platform coordinating", and push the project progress in real time through the mobile phone of the Zhengtong Weihai APP mobile phone. Give the person in charge of the project. Implement the alarm of blue, yellow, orange, red, and red -coded. Every day, lighting, monthly notification, and quarterly competition, supervise the districts and departments to analyze the roots, clarify measures, and follow up and catch it to the end.
As of the end of August, 810 city -level key projects have started 804, with a startup rate of 99.3%, and the investment is 77.48 billion yuan. The investment completion rate is 87.6%.
- END -
Investigate hidden dangers, keep safety, and promote development -Jinyang County, Liangshan Prefecture carried out special rectification of food safety in highway construction canteen canteen canteen construction sites
In order to further strengthen the food safety supervision of highway construction...
The Luding 6.8 earthquake has caused more than 30 people to kill the latest information here
At 12:52 on September 5th, a magnitude 6.8 earthquake occurred in Luding County, G...