Coordinates China | 30,000 tons of stations "moving" exquisite interpretation of "translation of accuracy"
Author:State -owned Assets Xiaoxin Time:2022.09.20
Xiaoxin said
In the past ten years, a series of heavy weapons and super engineering created by central enterprises have engraved new coordinates of national development from different dimensions. On September 12th, the online theme promotion of "our ten years@coordinates China" was officially launched. Over the major achievements of representative infrastructure construction and scientific and technological innovation, it shows the courage, courage and wisdom of challenging the limits and challenging the limit.
The main station building of Xiamen Houxi Coach Station is 162 meters long, 33.6 meters wide, 30,000 tons, and 288.24 meters. Rotate the world record. The transition rotation arc reaches 90 degrees, and the accuracy of the taxi is controlled within 2 mm, which is the first time in the industry. This time the "Qiankun movement" opened up the construction channel of the Fuxia high -speed rail. While saving construction investment, it also avoided a large number of construction waste, dust and noise caused by demolition and reconstruction. A vivid footnote. Today, Xiaoxin brings you the eighth issue of the "coordinate China" series theme films, and China's accuracy of "Transfer".
Fujian Xiamen Houxi Coach Passenger Station Translation Project
At 288.24 meters of translation distance
Certified by Guinness World Records as
"Buildings have the longest arc as a whole"
The construction area of the main station house is 22,800 square meters
Total weight of 3.018 million tons
Equivalent to 2.5 Arc de Triomphe
Realize 90 degrees rotation
Chinese architects
Will alternate step -by -step push and translation technology
The first time is applied to domestic translation engineering
Created the largest translation area in China
The heaviest load and the farthest distance
The most transit of single building
Part1
Why transit?
Xiamen is one of the earliest open economic zones in China
Is a tourist destination for the southeast coast of China
Xiamen in early 2019
Facing a difficult problem
Transportation hub outside the island
Houxi Coach Passenger Terminal
Because of the location
Re -coincide with the Fuxia Zhanggao Railway route
Facing the problem of demolition
To give way to high -speed rail
Mental argumentation of experts
It must rotate 90 degrees arc
Transfer to a new position
This is the best choice to avoid demolition
Part2
How difficult is the overall translation?
The overall migration project of the building
It has always been a difficult point in the field of infrastructure
This time passenger station translation is huge due to its huge volume
There is no precedent for success in the world
Theoretical calculation
Translation has the possibility of success
But overall migration
Need to solve two major problems
The first is to cut the pillar of the building
This process is also called broken base
If in the process of broken base
The construction is a little careless
It may cause
The collapse of the building that loses the foundation
Another important difficulty
It is in the process of translation
Accuracy control
Such a complicated architectural structure
Once unevenly suffered
Or pushing the thrust beyond the range of building tolerance
It is very likely to cause building damage
Part3
How to achieve accurate translation?
In order to ensure that the translation is successfully completed
The engineer finally locked the eyes
"Alternate step -by -step push translation" technology
The principle is through
Installation of steps at the bottom of the building
Make the building from the track stagnation
Unexpected settlement and other issues
There is no way to adjust the direction by yourself without angle restrictions
Multi -angle
Precise alternately walking forward
Just like the building has "foot"
Let the building "walk" along the track to the new site
The engineer chose after calculating
The second floor with a more stable support structure
Perform tower cutting
Pour concrete between columns
Form a solid mesh tray
The main building stairs break away from the foundation
It is taken down like a block
At the same time
Dig out a large foundation pit
Laying 26 arc concrete tracks
At the bottom of the main station
Installed 532 steps to perform the runner
How to ensure 532
The pace of a walking device is consistent?
Engineers will
603 sensors are placed to
The key position of each walkler
It's like 603 eyes
Watching the walking information of each walking device
Real -time feedback, real -time monitoring
532 Top Push of the Walker
Once the error exceeds 2 mm
The system will automatically call the police
Suspension
From 9 o'clock to 12 o'clock
30,000 -ton long -distance passenger station main station room
At a rate of 7.5 meters per day
Control of accuracy of not over 2 mm per step
Lotten 38 days
Cumulative 288 meters
Realized the perfect rotation of 90 degrees
Central enterprise engineer
With the original intention of craftsmanship, and struggling to take the mission
Pour the new image of China with the most reliable hands
Help to improve the "construction of China"
Brand reputation and global influence
Do you want to know which new era coordinates?
The next issue is equally wonderful!
- END -
Come, hold one with my brother ...
At 6 amMr. Wang, citizen, was awakened by a crying soundOpen the curtainI found th...
Provincial station "Guangzhou -Qingyuan Shitan" custom line is opened
On the 12th, the reporter learned that in order to facilitate the travel of the pe...