Fighting on the front line 丨 multi -blooming and cross -construction Mianyang High -tech Zone project construction staged the "optoelectronics" speed

Author:Chuanguan News Time:2022.09.17

Chuanguan News reporter Shao Mingliang

"Suddenly!"

On the morning of September 17, in the Optoelectronics Industrial Park in Mianyang High -tech Zone, a construction site that was under construction came out of the sound of pile driver. Close to the gate of the project, the "Gate Federation" of the blue -bottoming blue word reads 12 large characters "no delay in one day, and unlatmaking one day", which is particularly eye -catching.

The construction site of Ex Sen New Energy Industrial Park in Mianyang High -tech Zone.

"This is the first phase of the Exzon New Energy Industrial Park project, which is under construction, with nearly 200 workers' 24 -hour work." Zhou Lunwen, general manager of Mianyang High -tech Development Investment Holdings Co., Ltd., said that from July Since the start of the construction, the company's project special class has been "soaked" every day on the construction site, and spells its best.

Exxon New Energy Industrial Park is one of the 300 billion -level projects introduced by Mianyang this year, mainly producing lithium iron phosphate battery products. The project officially signed a contract to land in Mianyang High -tech Zone in May this year.

In the industry, this speed of advancement has already been considered efficient. Why should you emphasize the progress of grabbing?

Zhou Lunwen introduced that according to the construction progress of similar projects in Exxon, it usually takes 12 months to achieve trial production. However, in order to seize the product listing window period, seize the new energy storage battery track, project construction cannot be.

"Now it is the mid -testing line. This is the core part of the production of enterprises. According to the previous 12 months of construction period, it was already very nervous, but now the construction period is shortened to more than 4 months." Construction unit China Nineteen Metallurgical Group Co., Ltd. Li Chenglin, deputy manager of the project, said that he has been working for the first time for more than 30 years.

The medium test line is a medium -sized production line before the product is formally mass -produced, which has an experimental effect on product improvement observation. Its construction progress is directly related to the entry, commissioning and mass production of the device.

Getting progress, everyone is under pressure, but also full of power.

"The pile driver has increased from 6 in the past few days to 10." Li Chenglin introduced, "The newly added pile driver will be used to expand the work surface of the project construction of comprehensive stations and wastewater workshops to achieve multiple flowers."

The first phase of the Exxs New Energy Industrial Park project is undergoing pile engine construction.

While increasing the working surface, cross -construction is also a major "magic weapon" for the rapid progress of the project. "The so -called cross -construction is that we have a batch of sampling after the pile of the work surface. Shorten 20 days.

In addition to Exxon New Energy Industrial Park, another major project built in the Optoelectronics Industrial Park is also staged the same "optoelectronics" speed. The superstar group with a total investment of 28 billion yuan rare earth permanent magnet new material industrial park project, from negotiation to only 45 days of signing the contract, since the construction of July 29, it has completed more than 3 million cubic meters of earth and stone operations, which is equivalent to equivalent to equivalent to the equivalent The construction volume a day reached 60,000 to 70,000 cubic meters.

"We have built a full cycle, all -round, and 'nanny -nanny -type" nanny -nanny "service from negotiation, signing, factor guarantee, and construction of construction." The class is centered on the project, turning around the project, pushing the project to work, and sorting out the problems with the enterprise face -to -face.

It is understood that the Mianyang High -tech Zone is currently implementing the "industrial investment and project construction" operation. It is planned to build 2.4 million square meters of new modern plants within 2-3 years to create a new type of display and new energy and new material innovation industrial clusters to achieve realization. "Park quality" and "enterprise full garden". (Photo confession in the respondent)

- END -

Ministry of Water Resources: The Pearl River Basin Beijiang may occur on June 22

The Ministry of Water Resources will discuss the deployment of the Beijing River B...

The first overseas "lighthouse factory" in China's construction machinery industry is put into production

On August 15, local time, the first excavator produced by the Lighthouse Factory o...