The progress is refreshed!Baiyun 4 has made the latest progress in the construction of a subway line →

Author:Guangzhou Baiyun released Time:2022.09.15

Refresh! Refresh!

recently

Guangzhou Metro reports

The latest construction progress in the construction line

up to now

10 articles in the construction of a new line in construction

There are different degrees of update

in

Phase 2 of Line 7

And the No. 11 line of Baiyun

The cumulative completion of civil engineering projects exceeds 80%

Four of Baiyun's subway line under construction

Cumulative completion of civil engineering projects

84% of the Civil Construction of Metro Line 11

Recently, the Metro Line 11 ushered in the new progress of "penetration+starting": the left tunnel from Fangcun to Shiweitang range was smoothly penetrated, and the left tunnel from Nanshi Road to Yangang Division began to excavate.

Latest progress

A total of 84%of the civil engineering projects across the line. Of the 32 stations, 2 have been opened, 14 have been capped, 15 are under construction, and 1 of the remaining one is prepared in the preliminary preparations; 1 of the 32 areas has been built and opened, 18 have been opened, and 12 of the civil construction are carried out. Construction, the remaining one is prepared before construction. The construction of the Chisha vehicle section and the entry and exit section is carried out for civil construction. The three stations started the station decoration and mechanical and electrical installation construction.

Metro Line 12 realizes two tunnels to penetrate

Recently, the right -line tunnel from Tangxi to China Southern Airlines Xincun Xincun was successfully penetrated, marking the successful convergence of the two -cave area shields and excavation construction risks, and the dual -line of the interval tunnel penetrated. In addition, the "Qianjin No. 3" shield machine was unearthed in the secondary work area of ​​Mingwei Emperor Worgle District, the outer ring road of the University Town of Panyu District, marking the tunnel of the left line of the entry and exit range of the university city of the university.

Latest progress

Cumulative civil engineering projects have been completed by 50%. Among the 25 stations, 9 main structures were capped, 15 were under construction, and 1 preparation was carried out in 1 section. Of the 24 sections, 5 sections were connected, and the construction of civil construction was carried out. The remaining 8 were prepared before construction. The section and entry and exit section of the head, the South parking lot of the university town and the entrance line for civil construction. The rail engineering is under construction.

also

Two stations have a site in Baiyun

Metro route under construction

The progress is refreshed

Bleak

Phase II of Line 13 (Chaoyang-Fish Bead)

The cumulative civil engineering project was 54%. Among the 23 stations, 7 are capped, 15 are planned for civil construction, and 1 stations are prepared for preliminary preparations. Among the 23 areas, the six areas and the entry and exit lines of the Phoenix parking lot have been connected. Fish Parking Lot, Phoenix Parking Lot and Cover for civil construction.

Phase II (Jiahe Wanggang-Guangzhou Railway Station)

A total of 38%of the civil engineering project was completed. Among the eight stations, the four main structures were capped, two were construction in civil construction, and the remaining 2 were prepared for preliminary preparations. Of the 8 sections, 3 had been connected, 4 were carried out in civil construction, and the remaining one was prepared for preliminary preparations.

The rest of the construction progress of the subway line under construction

Dongyan section 3 (Panyu Plaza-Sea Piece)

The cumulative civil engineering project was completed 76%. Of the four stations, 3 were capped, and one of the remaining one was carried out for civil construction; 3 of the four sections had been connected, and the remaining one and the entry and exit lines were performed for civil construction. The construction of civil construction in Guangzhou New Town. The rail engineering is under construction.

Dongyan section 5 (Wenchong-Huangpu Passenger Transport Port)

The cumulative civil engineering project has completed a total of 72%. Among the 6 stations on the entire line, 4 stations have been capped and started mechanical and electrical construction, and the remaining two are carried out in civil construction; two of the 6 areas have been connected, 4 are carried out in civil construction; Essence

Phase II of Line 7 (University Town South-Northwest Water)

A total of 81%of the civil engineering project was completed. Among the 11 stations, six have been capped and started mechanical and electrical construction, and 5 of them are carried out in civil construction. Of the 11 sections, 9 have been connected, and 2 and the entry and exit sections are carried out for civil construction. The Jiotang parking lot is carried out in civil construction.

Line 10 (Xizheng-Shipaiqiao)

The cumulative civil engineering project was 52%. Among the 14 stations, 5 are capped, 8 are construction of civil construction, and 1 of the remaining 1 are prepared; 3 of the 14 areas have been connected, and 6 and the entry -exit section lines are carried out for civil construction. The remaining preparations are carried out. The construction of the vehicle section of the Guangsteel New Town is carried out.

Tongtong section No. 18 (村--Guangzhou East Station)

A total of 14%of the civil engineering project was completed. The construction of civil construction in the east to the village of Guangzhou.

Tongtong section of Line 22 (Chen Tougang-Fangcun)

Cumulative civil engineering projects have been completed 24%. Four stations are undergoing civil construction; one of the four sections is carried out in civil construction, and the remaining 3 are prepared for preliminary preparations.

Note: The name of the above stations is only the tentative of the project, and the standard station name shall be subject to the announcement of the municipal government's approval.

"Guangzhou Baiyun" WeChat Mini Program

It has been officially launched a few days ago!

Point a little bit

Learn Baiyun's new things

Bleak

Press the code and follow the code to follow

Watch the video, watch the live broadcast

See "Guangzhou Baiyun Release" video number

Popular video recommendation:

/>

<< Flying "Read" Baiyun: Watch Shanqing, Shuixiu &&

- END -

Herald reporter interviewed Li Ruihe, Chairman of the Board of Directors of Tianfu Group

When I first came to the mainland to start a business, I secretly made three wishe...

On July 29, 2 cases of new local diagnosis and 56 cases of infected infections were added in Shandong Province

From 0:00 to 24:00 on July 29, 2022, 2 cases of new local diagnosis were reported ...