The first batch of products went online smoothly!China Construction Eighth Bureau "Tsukin" Li Guilin High -tech and Manufacturing Industry In -depth integration
Author:China Construction Eighth Bure Time:2022.09.14
recently
Boarded by the Eighth Bureau of China Construction
Guilin Lingyi Intelligent Manufacturing Industrial Park structural parts plant
And supporting infrastructure (Phase I) Project
Completed the equipment debugging and the first batch of product production offline
"Building" Li Guilin's high -tech and manufacturing industry in -depth mutual integration
Ingenuity, the development of the service industry
The total construction area of the project is about 395,800 square meters
It is the key promotion project of "Double Hundred and Double New" in Guangxi Zhuang Autonomous Region
After the project is completed, it will become Guilin City
In the new development pattern
Bencing projects for realizing industrial transformation and upgrading
Accelerate technological innovation and high -tech for Guilin City
In -depth interaction with advanced manufacturing into the new driving force
After the project is fully completed and put into production in the first stage of the project
It will achieve from mold research and development to manufacturing
All -process production of injection molding, spraying, and assembly
Mainly used to produce vivo, Xiaomi, OPPO, etc.
Related well -known brand phones
And Daimler, GAC, etc.
New energy vehicle accessories, structural parts
Carefully plan, build a benchmark for the factory building
The project team adheres to the main line of construction schedules
Jianping planning as a prerequisite
Focus on safety and quality planning
Science and technology and green planning are guaranteed
Optimize construction technology
Reasonable allocation of people, materials, and machine resources
High -standard promotion project construction construction
BIM pipeline comprehensive ranking
Use BIM technology to intuitively optimize design
Ensure the construction, decoration and pipeline optimization of the construction of the plant
Avoid the risk of pipeline collision and demolition and reform
For the characteristics of the geological and geologicalforms and factory building of Guilin
Multi -foundation and use method
Coperly difficulty in dealing with a single infrastructure in Karst
Use heavy -loaded floor to directly set up the second floor of the inner frame construction
Replace the masonry wall with lightweight partition wall plate to reduce the number of secondary structural projects
Implement a number of large design and planning on the key line
Shorten the total construction period for more than 20 days
Lean management and control, promote efficient construction
The project team carefully summarizes the experience of previous large factory buildings
Choose an excellent approach to optimize the process
Promote the efficient construction of the project
Lingyi Intelligent Manufacturing Project is more past
The construction area is larger and the time spends less time
Refresh the record of "Guilin Speed" again
Hurrying in advance of the plate buckle material
Before construction, insist on "grain and grass first", plan the venue in advance
3,600 tons of hoarding plates, 1500 tons of reinforcement
50,000 templates, 300 cubic meters of materials and other materials and materials
Make sure that the impact of the epidemic and the shortage of market materials
Construction can be carried out efficiently at the scene
Combining process interspersed model
To achieve seamless gap flowing water construction
Realize the "zero nest work", and the cost of pressure and deprecation period
After the main structure is capped, the mechanical and electrical materials are installed simultaneously
Steel and processing of steel structures for curtain walls, coatings and decorative materials setting samples
Simultaneous construction of roof engineering
The work is methodical, the management is orderly and orderly
Come on against time, dry and fast
Since the project construction
Having overcome the tight construction period and poor geological conditions of Karst
Difficulties such as high technical quality requirements and heavy epidemic prevention and control tasks
In pile foundation construction, main structure, decoration
Electromechanical installation and other stages
Strictly control the handling of working faces between each process
The highest peak of the project staff reached more than 3,000 people
During the peak period, more than 2,000 people per day
More than 300 construction machinery more than 300 times
On the basis of ensuring safety production
Project builder charge forward
Surprove the big and fast -drying answers
The project completed the 180,000 square meters of main body ceiling in 2 months
The total output value was 725 million yuan in 5 months
Since the start of this year, 4 months have ranked 4 months in a bureau output value ranking
Winning a multi -sealing letter
Precise, strictly control construction costs
The construction of the plant has the characteristics of short, flat, and fast
The amount of funds is very large
The project insists on saving and saving, open source and throwing
Hold an operation analysis every month
Strictly control the construction drawing budget, weekly transfer, and on -site funding control
And follow up in time
Ensure the purchase cost of workers' wages and material materials
Take various measures to save materials
In the civil construction stage
Due to the actual use time of the external steel pipe, the actual use time is less than 3 months
The contract stipulates that the rent from 6 months
Caused a large amount of material idle and venue rental costs
By actively coordinating, actively provide venues and machinery
Use the secondary paint paint of the steel tube to make a weekly turnover
Reduce idle time and effectively save costs
Industry upgrade, expand happiness space
China Construction Eighth Bureau adheres to the careful and ingenuity
Help Guilin City with efficient construction
High -tech and manufacturing high -quality development
- END -
The 11th Chinese Painting Festival Four Great Full Full Full Drive, feed your eyes!
The 11th China Painting Festival of Weifang Daily, the 14th China (Weifang) Cultur...
The three departments have deployed to promote enterprise to absorb employment and social security subsidies "Direct and Quickly Office"
In order to increase the implementation of employment policies and promote the promotion of policies, the Ministry of Human Resources and Social Security, the Ministry of Education, and the Ministry o