The first batch of products went online smoothly!China Construction Eighth Bureau "Tsukin" Li Guilin High -tech and Manufacturing Industry In -depth integration

Author:China Construction Eighth Bure Time:2022.09.14

recently

Boarded by the Eighth Bureau of China Construction

Guilin Lingyi Intelligent Manufacturing Industrial Park structural parts plant

And supporting infrastructure (Phase I) Project

Completed the equipment debugging and the first batch of product production offline

"Building" Li Guilin's high -tech and manufacturing industry in -depth mutual integration

Ingenuity, the development of the service industry

The total construction area of ​​the project is about 395,800 square meters

It is the key promotion project of "Double Hundred and Double New" in Guangxi Zhuang Autonomous Region

After the project is completed, it will become Guilin City

In the new development pattern

Bencing projects for realizing industrial transformation and upgrading

Accelerate technological innovation and high -tech for Guilin City

In -depth interaction with advanced manufacturing into the new driving force

After the project is fully completed and put into production in the first stage of the project

It will achieve from mold research and development to manufacturing

All -process production of injection molding, spraying, and assembly

Mainly used to produce vivo, Xiaomi, OPPO, etc.

Related well -known brand phones

And Daimler, GAC, etc.

New energy vehicle accessories, structural parts

Carefully plan, build a benchmark for the factory building

The project team adheres to the main line of construction schedules

Jianping planning as a prerequisite

Focus on safety and quality planning

Science and technology and green planning are guaranteed

Optimize construction technology

Reasonable allocation of people, materials, and machine resources

High -standard promotion project construction construction

BIM pipeline comprehensive ranking

Use BIM technology to intuitively optimize design

Ensure the construction, decoration and pipeline optimization of the construction of the plant

Avoid the risk of pipeline collision and demolition and reform

For the characteristics of the geological and geologicalforms and factory building of Guilin

Multi -foundation and use method

Coperly difficulty in dealing with a single infrastructure in Karst

Use heavy -loaded floor to directly set up the second floor of the inner frame construction

Replace the masonry wall with lightweight partition wall plate to reduce the number of secondary structural projects

Implement a number of large design and planning on the key line

Shorten the total construction period for more than 20 days

Lean management and control, promote efficient construction

The project team carefully summarizes the experience of previous large factory buildings

Choose an excellent approach to optimize the process

Promote the efficient construction of the project

Lingyi Intelligent Manufacturing Project is more past

The construction area is larger and the time spends less time

Refresh the record of "Guilin Speed" again

Hurrying in advance of the plate buckle material

Before construction, insist on "grain and grass first", plan the venue in advance

3,600 tons of hoarding plates, 1500 tons of reinforcement

50,000 templates, 300 cubic meters of materials and other materials and materials

Make sure that the impact of the epidemic and the shortage of market materials

Construction can be carried out efficiently at the scene

Combining process interspersed model

To achieve seamless gap flowing water construction

Realize the "zero nest work", and the cost of pressure and deprecation period

After the main structure is capped, the mechanical and electrical materials are installed simultaneously

Steel and processing of steel structures for curtain walls, coatings and decorative materials setting samples

Simultaneous construction of roof engineering

The work is methodical, the management is orderly and orderly

Come on against time, dry and fast

Since the project construction

Having overcome the tight construction period and poor geological conditions of Karst

Difficulties such as high technical quality requirements and heavy epidemic prevention and control tasks

In pile foundation construction, main structure, decoration

Electromechanical installation and other stages

Strictly control the handling of working faces between each process

The highest peak of the project staff reached more than 3,000 people

During the peak period, more than 2,000 people per day

More than 300 construction machinery more than 300 times

On the basis of ensuring safety production

Project builder charge forward

Surprove the big and fast -drying answers

The project completed the 180,000 square meters of main body ceiling in 2 months

The total output value was 725 million yuan in 5 months

Since the start of this year, 4 months have ranked 4 months in a bureau output value ranking

Winning a multi -sealing letter

Precise, strictly control construction costs

The construction of the plant has the characteristics of short, flat, and fast

The amount of funds is very large

The project insists on saving and saving, open source and throwing

Hold an operation analysis every month

Strictly control the construction drawing budget, weekly transfer, and on -site funding control

And follow up in time

Ensure the purchase cost of workers' wages and material materials

Take various measures to save materials

In the civil construction stage

Due to the actual use time of the external steel pipe, the actual use time is less than 3 months

The contract stipulates that the rent from 6 months

Caused a large amount of material idle and venue rental costs

By actively coordinating, actively provide venues and machinery

Use the secondary paint paint of the steel tube to make a weekly turnover

Reduce idle time and effectively save costs

Industry upgrade, expand happiness space

China Construction Eighth Bureau adheres to the careful and ingenuity

Help Guilin City with efficient construction

High -tech and manufacturing high -quality development

- END -

The 11th Chinese Painting Festival Four Great Full Full Full Drive, feed your eyes!

The 11th China Painting Festival of Weifang Daily, the 14th China (Weifang) Cultur...

The three departments have deployed to promote enterprise to absorb employment and social security subsidies "Direct and Quickly Office"

In order to increase the implementation of employment policies and promote the promotion of policies, the Ministry of Human Resources and Social Security, the Ministry of Education, and the Ministry o