Shijiazhuang Fuxing Street Municipalization Reconstruction Tunnel's main body construction is promoted in an orderly manner

Author:Shijiazhuang Daily client Time:2022.09.09

Ji Shi client reported (Xing Yusen, a correspondent in Du Yanqing Wang Yan, Hebei), as a key project of Shijiazhuang City, the main project of the three tunnels is promoted at full speed.

On September 9, the reporter visited the construction site of the Municipalization Reconstruction Project of Fuxing Street, Yingximen Tunnel, White Buddha Tunnel, and Xueyuan Road Tunnel. It can be seen that the people at the scene were crowded, cranes, and roar of mechanical machines, shuttle vehicles traveling through, and the main construction of the tunnel's main body has begun to take shape. After completion, it will enter the construction phase of the buried section. According to the responsible comrades of Shijiazhuang Traffic Investment Group, as of now, the pilot project of the Municipalization Reconstruction Project of Fuxing Street has been completed on July 31. The three tunnels have been fully entered the main construction stage. The pile foundation was completed by 10%; the road -based project clearance was completed 78%, the excavation party was completed 24%, and the filling party was completed by 16%; the pavement project is undergoing underground grassroots and grassroots construction.

"At present, the municipalization reconstruction project of Fuxing Street has invested more than 1,100 on -site construction personnel and more than 440 mechanical equipment. Since August 25, more than 600 tunnel enclosure piles have been completed, more than 30 grid columns, and the main body of the tunnel tunnel. About 130,000 cubic meters of excavation, at the same time, the construction of stools, steel bars, bottom plates and internal support, and accelerate the main construction of tunnels. " , Grasp the construction organization, continue to set off all the work surfaces and quickly go up, and go all out to promote the construction of the project. By the end of October 2023, the main project of the Xueyuan Road Tunnel and the White Buddha Tunnel will be completed. structural work."

The total length of the municipalization project of Fuxing Street is 35.4 kilometers. Through municipalization, Fuxing Street will build a two -way 12 -lane municipal road from Anji Road to the South Third Ring Road section. Among them The width of the main road is 33 meters, and the main auxiliary band is 10 meters on each side, each of which is 16.5 meters auxiliary roads; the remaining sections are upgraded to two -way 8 -lane expressway. There are 11 interchanges across the line, connecting 9 expressway and 2 main trunks; 16 pairs of imports and exports, connecting 12 main roads in cities.

According to the plan, the municipal transformation project of Fuxing Street will be opened to traffic in 2024. At that time, Fuxing Street will jointly build a skeleton road network that pulls the big city framework and support the development of the group with the intersection roads along the route, forming an external traffic road network system with smooth and internal and interval integration. In -depth integration with the Luohe Economic Belt and the Taihang Mountain Ecological Belt, helping Shijiazhuang City to build a city of charm of local people and longing for foreigners.

Source: Hebei Radio and Television Station Jishi Client

- END -

Five -year development review of Zhejiang Red Cross: Humanity Consultation

Zhejiang News Client reporter Wang Chenhui Correspondent Li YipingThe raising soci...

Water Quality Supervision Cadres top day running project, "the more high the temperature, the more tight the responsibility string"

The scorching sun shines on the construction site by the Yangtze River, and the gr...