"Strive for strong provincial capitals to welcome the 20th National Congress" promotes the development of high -speed rail construction

Author:This is Ningxiang Time:2022.09.06

today

The Changyi Changchang high -speed rail Yizhuang, which lasted three years, has been opened to traffic

This also marks the official entering the high -speed rail era!

The construction of high -speed rail can not only shorten the time and space between cities and cities, and expand the radius radius of the city, but also an important promoter of regional economic coordinated development.

In 2018, as a full -time responsible for the construction of key national and provincial key engineering construction within the city, the city's key engineering service centers (formerly municipal investment promotion service centers), which is the planning dynamics of key engineering projects, captured the planning dynamics of key engineering projects, captured the capture After the Changye high -speed rail will lay out the information on the construction of Ningxiang, it will quickly seize the opportunity of construction, strive to start from the planning session, and optimize the construction environment through effective measures such as coordinating management, early intervention, and tracking services. Optimized the development pattern of Ningxiang City, and injecting new vitality into the sustainable and healthy development of the city in the city.

Intervene in the high -quality development of Ningxiang in advance

"For the high -speed rail route and site selection, we have spent a lot of effort." Talking about the early work of the project construction of the Changyi Changye high -speed railway Ningxiang section, Deng Xinhua, director of the Municipal Key Engineering Service Center, couldn't help feeling.

The Changye high -speed rail is located in the northwestern part of Hunan Province. It is located in the Changsha -Yiyang -Changde Urban Industry Everbright Belt. From the Changde City of Changde City in the west, it is 162.79 kilometers in the east, with a total length of 22.42 kilometers. From northwest to southeast, Changde Station, Hanshou South Station, Yiyang South Station, Ningxiang West Station, and Changsha West Station. Ningxiang West Station belongs to the newly built, located in Jinghua Pu Township, with the north horizontal line east, west of Chuncheng North Road, south of the stone long line, north of the station, about 4.4 kilometers from the main urban area, and about 2.5 kilometers from Ningxiang Avenue.

Initially, the Changyi Changchang High -speed Railway Ningxiang section designed the southern and northern lines. Subsequently, the northern line plan was initially determined. After analysis, it was found that the North Line Program Station and existing railway stations were implemented in parallel, which caused cutting impact on the land of Ningxiang Economic Development Zone, which is not conducive to regulating the use of land in the future. The Municipal Key Engineering Service Center went to the Ministry of Railways and the Fourth Court of the Railway for reports, and invited experts such as the Fourth Court of Railway Hospital to conduct multiple research and demonstrations on the route direction of the Changyi Changchang Gao Ningxiang section and the site site selection. In the end, the Railway Corporation adopted the South Line plan to determine that the new high -speed rail station -Ningxiang West Station was set up in our city, and the address was determined according to the intention of the Municipal Party Committee and the Municipal Government.

The new Ningxiang West Station is based on the original design. In principle, the area of ​​the station is generally controlled at 2500-3000 square meters. Considering that Ningxiang has developed rapidly in recent years, and the transportation network has continued to improve, in the future, Ningxiang West Station will become an important transportation hub. The city's key engineering service center has reported and coordinated. Meter.

"The determination of the location of the station and the expansion of the area is not only conducive to transportation organizations, reducing congestion, enhancing the image and taste of the city, and helping to stop the number of trains in the future, which is convenient for the masses to travel. The parallel and interoperability of the South High -speed Railway also reserved a full space for the future development of Ningxiang. "Deng Xinhua said.

In the process of project promotion, the Municipal Key Engineering Service Center gave full play to the role of staff, always paid attention to dynamics and analyzed the actual situation of Ningxiang, and promptly and actively connected and coordinated to maximize the development of Ningxiang.

In March 2020, due to the cutting of the region of the high -speed rail and affecting the future development of Ningxiang, the high -speed rail crossing project must take into account the stability and safety of the high -speed rail construction. The procedures are complicated and complicated, and it is even more difficult to go through the later period. The center quickly acted, took the initiative to report the situation with the municipal party committee and municipal government. Immediately, the mayor has repeatedly led the heads of the city's key engineering service centers, the Natural Resources Bureau, Ningxiang Economic Development Zone, Ningxiang High -tech Zone and other relevant departments to conduct on -site surveys. After several adjustments and modifications, the preliminary plan was finally formed. The road, Corning North Road, Chuncheng North Road, Huaming North Road and other ten settings under the passage. In the end, the plan was recognized and implemented by the iron line design, Hua Shaoheng company and other units.

"Because of these down -through channels, the traffic advantage has brought together the future development of Jinzhou New Town!" Deng Xinhua told reporters that while organizing and coordinating budgets, financial reviews, and security evaluations, it was promoted smoothly. Channel construction ensures simultaneous advancement with the construction of high -speed rail, and is completed as scheduled.

Intimate service promotion project construction runs out of "Ningxiang speed"

The construction of the Changyi high -speed high -speed rail is not only a measure to improve the Ningxiang Dahaongong Traffic Network, but it will also play an important role in the new journey of Ningxiang's "Construction of the Provincial Excellence and Entrance to the top ten nationwide".

The Municipal Party Committee and Municipal Government attaches great importance to this. All towns and towns along the line have clearly in charge of leadership and established a coordination headquarters. Municipal leaders conduct high coordination of the project and personally check; the city's key engineering service center gives the project a full range of high -quality services before the project construction, during the construction, and after construction, and fully promotes the project to build and build it quickly.

"We arranged two staff members to form a service team to coordinate services throughout the process." Deng Xinhua told reporters that in order to actively optimize the construction environment, do a good job of project construction "one -stop" service, Changye high -speed rail construction construction From the end of the brewing to the end of the tail sweeping, whether it is the docking of relevant provincial and municipal departments, or the connection of the units such as survey, design, construction, construction, and the procedures for the procedures of various departments and units The maintenance of this service team is full -time, which not only guarantees continuity, enhances the sense of responsibility, but also establishes a good image. The project can be successfully constructed. However, key engineering projects are large, wide, and large in number, and they need to be harmonious, efficient, and safely demolished, so that the national engineering is not damaged and the masses do not suffer.

In August 2019, in order to ensure the successful construction of the project, in the case of insufficient budget funds for the project, especially in the case of insufficient funding for enterprises in the park, the center of the center scientifically coordinated, actively coordinated, and rely on services. In the end, 212 was completed within one month. The demolition work of buildings and 6 companies.

"Solving the temporary land use problem of the beam -making field, the project construction speed will not be delayed!" Chen Huihu, deputy general manager of the 24th Bureau of China Railway, told reporters that in August 2020, in order to speed up the project construction speed, the original China Railway Twenty -four Bureau original originality The beam -making farm can no longer meet the needs of construction, and urgently need to use land to build a new beam. After learning about the situation, the Municipal Key Engineering Service Center took the initiative to dock, coordinated the temporary land in the Ningxiang Economic Development Zone, opened the second beam -making farm, and coordinated the relevant procedures half a month in advance. Essence

Since the construction of the Changyi Changchang High -speed Railway Ningxiang section, the Municipal Key Engineering Service Center will track the entire process of project construction.

On February 27, 2020, the reporter saw at the construction site of the sixth standard section of the Ningxiang section of the Changye high -speed railway.

In order to ensure the successful resumption of the project, starting from January 23, the main leaders have implemented a rotary lead and each headquarters will arrange personnel to work every day, hold a special scheduling meeting of epidemic prevention and control, and guide and urge all construction units The department requires the implementation of the epidemic prevention and control work. At the same time, special personnel will be arranged as projects for epidemic prevention liaisters to help purchase masks and disinfection of epidemic prevention materials, and guide the development of epidemic prevention knowledge, office and construction site disinfection, and ensure that the entire line is fully safe to restore construction.

"The Anling Tunnel is a controlled project. The time is tight and the tasks are heavy. They are all conducting operations for 24 hours. The "meeting division" at both ends of the exit, two months earlier than the original plan. This also marks the smooth penetration of the only second -level risk tunnel of the Changyi high -speed rail -Aling Tunnel.

While ensuring the progress of the project construction, it is also necessary to safeguard the legitimate rights and interests of the people. Since the construction of the project, the Municipal Key Engineering Service Center has adhered to the "people -centered people" and faced the problems such as water and sand pressure, highway damage, house shocks, and noise pollution brought about by the project construction. The spirit of tiredness and dare to fight hard ", from early morning to late at night, visited home from home, recorded the demands of the demolished households. At the same time, from the actual development of local development, actively coordinated and connected to the Guangtailian Group, Huai Shaoheng Company and various target sections to hold more than 300 dispatch meetings. The reasonable demands of ordinary people along the project were basically resolved, and more than 4,000 problems were coordinated.

Thousands of triads to guarantee high -speed rail to open operations safely as scheduled

On September 2nd, in front of Ningxiang West Railway Station, Deng Xinhua explained the precautions with the relevant person in charge, while communicating with the staff of the city's key engineering service centers, to communicate the guarantee service in the future.

Since the Changye Changchang high -speed rail entered the joint testing stage in April, the Municipal Key Engineering Service Center has closely focused on the goal of the smooth opening of the high -speed rail. , Topicians to complete the preparations before the opening of the traffic.

"Clean up and renovate the hidden safety hazards of the outside of the line outside the line, and improve the safety environment along the railway." Due to the high requirements of the high -speed rail safety opening and operation, the surrounding environment is high. The townships (streets) along the line are timely rectified through light floating objects such as dangerous trees, dangerous bamboo, plant lighting tiles, vegetable greenhouses, and colorful cloths. Especially in Ningxiang Park, due to the insufficient fire protection distance of many companies, it is necessary to transform it in technology. The Municipal Key Engineering Service Center communicates with multiple parties such as enterprises, design units, railway departments and other parties. The tunnel trial headquarters coordinated on -site and formulated internal and external rectification plans. In the end, the 345 safety hazards along the line were fully rectified, and the safety "firewall" of the high -speed rail was firmly established.

"The construction of the station was started in February this year. At the end of July, it was required to meet the traffic conditions. Time and task were heavy!" In February of this year, the construction of the Changyi Changchang High -speed Railway Ningxiang West Station Station was started. The center concentrates its strength and organizes the construction of the construction units such as the City City Group. Especially since the end of June, the project has entered the sprint stage. The staff of the center has worked overtime day and night to coordinate the problems encountered during the project construction process. At the end of July, the environmental improvement and construction of the Changyi high -speed railway were successfully opened. Planning, construction, tackling, management, innovation ... Every level of the completion and traffic of the Changye high -speed rail project has gone through various choices and tests to witness the wisdom and dedication of the people of Ningxiang projects. Vitality.

(Duty leader: Yu Bo review: Su Jian coordinated: Liu Shijiang Source: Rong Media reporter Peng Feng Correspondent Hu Guangzhi, Editor: Xiang Lei Hong)

Don't miss these wonderful content!人 Zhang Zuolin emphasized when investigating the work of the Municipal People's Congress: attaches great importance to and supports the work of the people's congress to promote the high -quality development of the people's congresses. "Fast", efficiently promote the "100 -day tackling" special action for self -built houses

- END -

Can the live broadcast work bring more workers to the factory?

I am busy recruiting in the live broadcast room, hundreds of thousands of people watching the factory online, and receiving more than 100,000 resumes within 2 hoursCan the live broadcast work bring mo

Anhui Institute of Information Engineering held a new professional application review meeting in 2022

On July 5th, the Academic Affairs Office of the Anhui Institute of Information Eng...