The Wa Ri Line Expand Autumn Concentration Repair
Author:Smart Life News Time:2022.09.06
(Reporter Gao Huijuan Correspondent Zhang Jiong) At 6:50 on September 5th, the 20 -day autumn concentrated construction was fully carried out on the Wati Railway line from northwest to southeast of Shanxi Province.
From the same day to September 24, China Railway Taiyuan Bureau Group Co., Ltd. arranged for 180 minutes to conduct centralized construction operations such as large -scale maintenance and treatment in the tunnel, and quickly restore the quality of line facilities and equipment after summer high load operation.
Watri Railway west of Watang Town, Luliang City, Shanxi Province, via Henan Province, and finally to Rizhao City, Shandong Province. It is the first railway line to build in China and directly meet the international heavy -duty railway standards. Important channel. During the summer and August of this year, the Taiyuan Bureau Group Corporation Guan Genesis Railway has transported more than 1,455 million tons of coal. Since this year, it has transported more than 60 million tons of coal, an increase of 8.2%year -on -year.
During the concentrated construction, the Taiyuan Bureau Group Company will focus on using large construction machinery, 160 kilometers of mounting lines, 118 campaign forks, 120 kilometers of polishing lines, 129 grinding roads, and rectify tunnel diseases to signal machines and contacts Ways such as networks and other equipment for comprehensive maintenance.
Due to the current transportation task and strict requirements for the prevention and control of the epidemic, during the centralized construction period, Taiyuan Group Corporation established a site construction headquarters in Linfen to coordinate manpower, power, and material resources, reasonably arrange construction projects, assign special personnel to pay close attention to the former personnel to go to the way to go to the way. The dispatch command is delivered, the blockade, the construction organization, the construction organization, the train release and other key links to ensure that the various tasks during the centralized renovation period will be carried out smoothly.
In order to ensure the safety and efficiency of transportation during construction, the transportation and dispatching department of the Taiyuan Bureau Group Company rationally compiled the daily (class) plan, accurately and timely issue the train operation adjustment plan, and improve the daily class plan. The comprehensive section of Linfen strengthens transportation organizations, optimizes operating procedures, unblocked information, reasonably arrange to use the use of hairline and vehicle technical inspection operations to ensure that transportation is efficient and unobstructed during construction. At the same time, the motorcycle operation time is scientifically adjusted, while the quality of locomotives during construction will be improved, and energy transportation will be guaranteed during construction.
It is understood that the current central and Korean lines of the Taiyuan Bureau Group Corporation are also being carried out simultaneously.
- END -
Haidian District Commercial Federation launches "righteous cutting into the first line" activity
A few days ago, under the premise of strictly abide by the various epidemic prevention policies at this stage, do a good job of personal safety protection, and maintain a safe distance, it organizes J
Shandong Rizhao: "Beautiful Industry" promotes rural revitalization
On August 4, the technicians were instructing villagers to arrange flower arrangem...