The 100 -ton "Big Mac" Qi Yun Kerry Logistics escorted the Xilhe project
Author:China Economic Network Time:2022.09.06
A few days ago, the 1500MW Gas Circular Revolution of Gas Revitalized Power Station Project Project (hereinafter referred to as the "Sirhe River Project"), which was carried out by Kerry Logistics, has spanned the fourth important milestone -the major projects of the project's main equipment are all all the major items of the project equipment. Started from native country.
It is understood that the Syr River project officially signed a contract in January 2021. The owner is ACWA Power, the Saudi Power and Water Development Corporation, and the EPC general contractor is China Energy International Group. As the "Uzbekistan's first foreign IPP project", the H -class gas turbine with the highest combustion temperature, the largest single power and the highest efficiency in the world and the "zero discharge of wastewater" design schemes in the world Green Energy Sales and Environmental Protection Power Station. At the same time, as the "Chinese -funded enterprise signed the first gas joint cycle power station project in Uzbekistan", "Uzbekistan has signed the largest burning machine project in recent years", it will also be constructed as a "Belt and Road" model project.
Kerry Logistics officially signed the main equipment section of the Xilhe River project in August 2021. The work scope includes two gas turbines (including residual heat boilers), one steam turbine and three startup transformers. In order to welcome "Uzbekistan's most difficult transportation work in recent years", under the leadership of the EPC chief contractor, the company exerts its own network resources advantages, cooperates with members of various regional members of the group, quickly forms a project team in the world, and officially forms it. After signing the contract, the epidemic rushed to the scene as soon as possible, carried out preparations for implementation, and promoted the implementation of transportation resources.
In November 2021, as a local land transportation port to the main freight channels to Uzbekistan, it strictly implemented the control measures of import and export vehicles. This measure made a significant contribution to the control of the epidemic. Here comes severe challenges. With the support of the owner Acwa Power, and the leader of the EPC Chief Container China Energy Construction International Group, Kerry Logistics Collaborative Group SF Railway Platform Company, with the China Customs Customs Association, constantly comes with Urumqi Customs, Holgos Customs, Uzbekistan, Stan's Consulate General in Shanghai and the local railway bureaus of China Railway conducted communication to promote the shipping of the project.
From December 2021 to August 12, 2022, due to the power restriction incident in some regions of China, the new crown epidemic situation was superimposed, and the main equipment supply chain of the project was seriously affected. In order to reduce the impact of the objective environment on the supply chain as much as possible, the EPC and Kerry Logistics Project Team carried out a flat management model. Relevant responsible persons directly reached the coordination of the production front line and the factory to master the progress of progress in real time. Make sure that the main equipment will all enter the goal of the canal during the year.
According to the relevant person in charge, on February 24, 2022, the Syl River project ushered in one of the biggest challenges since construction. The tension in the region has a direct impact on the transportation of major equipment. In order to ensure the delivery of the project as scheduled, the owners, EPC, and the members of the Kerry Logistics Project Team have started the close collaboration of nearly half a year. On the one hand, coordinate the shipping company to change the ownership of the ship to meet the transportation permit requirements. Finally, at the end of July 2022, it reached an agreement with all relevant parties, completed all the front conditions of the main equipment transportation, and successfully opened the second section of the transportation work of the main equipment.最终确认的圣彼得堡路线,将全程运输距离拉长至28000公里,达地球最大直径的70%,结合在中亚地区的2200公里内陆运输、多达67处的新建桥梁、维修桥梁、道路修建、 Road barrier work.
- END -
What is the harvest of the summer tourism market in 2022?The major OTA data can be seen at a glance
21st Century Business Herald reporter Gao Jianghong intern Feng Zhixin Beijing reportAs the major and secondary schools started schools one after another, tourism in 2022 also ended. Recently, major O
The protected area is arid, Zimbabwe moves more than 2,600 wild animals
Zimbabwe is moving for more than 2,600 wild animals such as elephant and giraffe, ...