Zhejiang was restored by Typhoon "Xuan Lannuo" affected power supply

Author:Zhejiang Daily Time:2022.09.05

Zhejiang News Client Correspondent Zhang Zhenghua Chen Lisha Zhang Zifan reporter Zhang Fan

As of 17:00 on September 5th, Zhejiang's affected by Typhoon "Xuan Lannuo" has restored power supply users. Although Typhoon "Xuan Lannuo" did not log in, it brought strong winds and rainfall to local areas of Zhejiang, and some people were affected by electricity. State Grid Zhejiang Electric Power dispatched 17,000 people to carry out repair and inspection for the first time.

On the afternoon of the 5th, a 12 -level wind appeared in Zhoushan City and dropped rain. In Shuangqiao Town, Dinghai District, an outdoor lead was blown off by wind, the drainage pumping station could not work properly, and drainage and drainage were affected. State Grid Zhoushan Power Supply Company rushed to the scene for the first time. After 100 minutes of intensive work, the break was re -completed, and 420 households such as drainage pumping stations resumed power supply.

Affected by the typhoon "Xuan Lannuo", Ningbo Pu in Zhejiang was raining, and the line in Bailu Village, Luting Township, Yuyao City failed, and about 100 residents were affected. After the repair personnel turned over the hillside, after the inspection of 44 electric poles, the reason was that the reason was that an electric pole porcelain bottle was broken and the emergency replacement was carried out. After two hours, the line returned to normal power supply.

Chen Chaoyang, secretary of the party branch of Liang Ni Power Supply Center of the State Grid Yuyao City Power Supply Company: "The Siming Mountains are large, and there are no roads in many places. Many times we can only use sickle to open the road. At present, we have a large water vapor on the mountains. It is very low. In order to find the fault as soon as possible, we can only climb to the top of the pole to find the fault. In order to let the people use the electricity as soon as possible, we are worse. "

Affected by the typhoon, the 11th -level wind in Taizhou was scratched, which led to a warning information of the line switch of the Toumen Port Wharf's operating area. After 30 minutes of elimination and re -debugging, the switch resumes normal operation.

On the evening of the 4th, the wind caused the power supply of villages and farms in Qiantang District, Xiaoshan District, and Tonglu County in Hangzhou City. Power repair personnel were affected. Power repair personnel used the weakening of wind and rain to carry out emergency repair, timely repair equipment, and restore power supply. During the command of the Director of the Power Supply Center of Tonglu County Power Supply Company of the State Grid, I said during the command of the command: "Because this Xuxi No. 1 public change is in the middle of the field, our forklifts and cranes cannot reach Come on the installation, move the transformer to the specified position, and then hang the transformer with your hand to hang the transformer. "

In order to cope with the typhoon "Xuanlan Nuo", the State Grid Zhejiang Electric Power dispatched a total of 17,000 repairers, 7,460 vehicles, and inspected 2471 substations and more than 27,000 Taiwan areas to carry out line channel cleaning and hidden dangers. The province's power supply is normal.

- END -

Weifang Xiaci Cultural Tourism Market has a new trick: "Fireworks Qi" warm field "Experience Tour" singing protagonist

Cloudy for a while, with the popularity of the night economy, the recovery of cult...

Taiyuan: Strictly check the quality of nucleic acid testing for third -party nuclear inspection agen

On June 8th, the Municipal Health and Health Commission issued news that the five...