The State Council Supervisory Group coordinated the "block"
Author:Xinhuanet Time:2022.09.03
Xinhua News Agency, Hohhot, September 2 (Reporter Feng Jiashun) Recently, the 9th Supervision Group of the State Council's ninth inspection team was on -site to coordinate multiple parties to help Inner Mongolia Hohhot's heating heating project to open the approval of "blocking points" to ensure the warmth of the masses winter.
It is reported that the 2 × 660MW unit of the Jinshan Power Plant in Inner Mongolia Shengtai Heating Power Co., Ltd. is a supporting heating pipe network project. It is a national 300 billion yuan policy development financial tool support project and a livelihood project for Hohhot heating heating.
The inspection team learned that this project crosses the railway route, the application procedures are complicated, and the process will take two months as soon as possible. The start time will be postponed until October. Inner Mongolia's winter frozen soil is more difficult, and the extension of construction will have an impact on residents' winter heating.
The inspection team rushed to the scene to coordinate local governments, railway departments, and project units. The inspection team believes that the "blocking point" of the project is mainly due to the long period of processing the procedures. After studying and analyzing with the technical personnel of the railway department and comprehensively, the inspection team proposed a "tolerance for handling" method, that is, the preliminary examination of the construction map, etc., and approved it after the preliminary examination. Construction as scheduled.
Through the joint efforts of various parties, the project unit successfully obtained the "Reconstruction of the Railway under the Heating Pipeline of Shengtai Heat Co., Ltd. in Inner Mongolia", which was at least one month earlier than the expected time, laying a good foundation for construction as scheduled.
According to the person in charge of the Jinshan Power Plant's supporting supply network project, the current project procedures for project project procedures and the progress of the bidding work are progressing smoothly, and the project can start before the end of September. This year is expected to complete the construction project of some construction section of the construction section, and the heating area can be connected by about 2.3 million square meters. Among them, about 80%of residential residential houses are expected to benefit more than 15,000 residents.
- END -
Under the driving of wind and heat -polyetheric: Listing enterprises are busy expanding production
On August 9, Shandong Longhua New Materials Co., Ltd. issued an announcement that the construction content and scale of the amino polyether (polyetherine) project were adjusted to change the construct
Shandong comprehensively implemented the "Pass House Accepting House" system
Provincial Housing and Urban -Rural Development DepartmentRegarding the comprehensive implementation of the Receive House after the Priority House systemNotice to promote the quality of the delivery