good news!There are new changes in these roads in Wuhan

Author:Changjiang Daily Time:2022.06.19

recently

On a message board in Wuhan City

Some netizens consulting the road construction progress near the consultation

Relevant departments replied

See if there is any near your home

↓↓↓

1. Netizen: When is the opening time of Beacon Road?

Hongshan District: The Fire Road Road Project is currently completed from Zhangjiawan Road to Wuliang Road. The main lanes and people's roads have been completed from Zhangjiawan Road to Yangsi Port section. The road engineering plan is planned to be completed in June 2022, and traffic will be opened after the experience is received. Hongshan Construction Investment Co., Ltd. is actively coordinating and urging relevant units to speed up the progress and strive to open the traffic on the beacon road to serve the surrounding residents.

2. Netizen: When will the roads and roads leading to Zhuye Sea Park on the road of Wason Park Avenue of Mantou?

Tongkou District: After verifying the specific situation of the survey, Chenghua Road is currently undergoing supporting street lights. After the supporting construction is completed, traffic will be opened.

3. Netizen: When will the internal road of Sunshine Valley be delivered?

Jiangxia District: On November 17, 2021, the traffic brigade came to investigate on -site investigation. The main problems were concentrated in the lack of corresponding traffic equipment (traffic signal lights, electronic police, video surveillance, etc.). The acceptance was completed on the 27th, and the application for application for opening to the higher authorities has now been submitted to the superior department. It is expected that the road can be opened in the near future.

4. Netizens: How about the progress of Baisha Second Road?

Hongshan District: The current power relocation is being designed. It is planned to implement the power construction unit in June. The Baisha Second Road Project is planned to be completed by the end of this year.

5. Netizen: When will the left bank Avenue Mountain from the Wanjia Lake be opened to traffic?

Wuhan Economic Development Zone: Left Bank Avenue (Wanjia Hunan Road -Xiajun Mountain) construction project contract period 2 years (September 2021 -September 2023), which is expected to open to traffic by October next year.

What else do you want to consult about the progress of municipal engineering planning? Welcome to leave a message in the comment area or go to Wuhan City Message Board sharing

Yangtze Daily Da Wuhan client product sorting: Deng Yao editor: Cheng Jiayi school pair: Mao Xin

For more exciting content, please download the "Da Wuhan" client in the major application markets.

- END -

Just tonight!

According to astronomical popular science experts, a round of Super Moon will appe...

Guazhou: New Chapter of Cultural Huimin Tianjia Cultural Tourism Federation Spectrum

Bamboo deep tree dense insects are crying, and it is not cold. In the midsummer, a...