my country's first cross -sea high -speed rail is connected across the board!
Author:Gansu daily Time:2022.08.30
On the morning of August 30th, at the construction site of Xiamen North Station, Xinfuxia Railway, with the successful layout of the last set of 500 meters long rails, my country's first cross -sea high -speed rail -Xinfu (State) Xiamen (Gate) Railway Lauret was connected throughout the line. Essence
The newly -built Fuxia Railway Meizhou Bay Cross -sea Bridge (drone photo) was built on April 15, 2022. Xinhua News Agency reporter Zhou Yi Photo
According to the relevant person in charge of the China Railway Nanchang Bureau Group Co., Ltd., due to the complex hydrological environment and high risk factor, there are three difficult construction locations in the entire line of the Fuxia Railway. Cross -sea bridge. To this end, the construction unit adopts the domestic advanced two -tier rail paving operation equipment, and the long -sized rails on the left and right lines are laid at the same time, which is 60%of the operating efficiency of 60%compared to the traditional rails. The railway opens a solid foundation on schedule.
It is understood that the design of the Fuxia Railway is 350 kilometers per hour, and the main line is 277.42 kilometers. There are 8 stations on the entire line. After the railway is completed and opened to traffic, Fuzhou and Xiamen will realize the "one -hour life circle", and the "Golden Triangle" of Xiamen, Quanzhou, and Zhangzhou Fujian will form a half -hour traffic circle.
Source: Xinhua News Agency
Editor in charge: Yu Shuai
Supervisor: Mu so strong
- END -
Kuiwen District builds a digital flood prevention command system to build flood control safety dams
Kuiwen District is located in the central urban area. Flood prevention and typhoon...
What are the legal consequences of Enping's enterprise illegal operation?Tomorrow this episode tomorrow!
Safety production is an enterpriseThe source of life and benefitsSafety production...