No property registration certificate, construction land planning permit, construction project planning permit, qualified documentation documents, residential construction permits, construction engineering construction permits, 6 certificates will be issued in half a day, and the construction team will enter the next day the next day. Start. This is the process of the "Getting Land" project in Lanshan District -Xinglan Port Service Co., Ltd., Lanshan District, Rizhao City, just experienced the process.

In the past, from land acquisition to obtaining construction permits, it was necessary to go through the approval review of multiple departments and more than 20 links. It took about half a year to take the approval process.

At present, the time limit from "1 0 0 +" to "0.5" has been the normal expression of "starting the land" since the "169" of the Lanshan District. Behind it is the comprehensive effect of "running", "accelerated" and "joint force" in the Lanshan District service project.

The four departments of the Natural Resources Bureau of the District, the Planning Service Center, and the District Housing and Urban -Rural Housing and Construction Bureau of Lanshan District have set up project service teams to set up project service teams to take active on -site services, face -to -face counseling, and tolerance simulation pre -review. "Working period". Effective use of project land transfer statutory announcements, listing and planning publicity time, to obtain the project construction license as the time node, integrate the approval process into four stages: project confirmation, material preparation, simulation review, and unified certificate issuance, break the department and stage restrictions , Implement the full process parallel approval.

During the approval process, the district's administrative examination and approval service bureau will provide information on the application materials, approval process and other information of the project approval of the project approval. And hold a joint meeting in conjunction with the company's own situation, implement "one -to -one" on -site counseling, coordinate the land, planning, civil defense, bidding, drawing, and construction permits. Prepare before approval.

"On the surface, the" multi -certificate "of the project was completed in half a day. In fact, we have made many work before, making the scheme before the review, and the service before the approval." Zhang Guangzhi, director of the Administrative Examination and Approval Service Bureau of Lanshan District, said Essence

It is understood that in order to further improve the efficiency of approval and service, Lanshan District will pass the "low -risk project exemption", "special window service", "front", "parallel", "tolerance" and other innovative work processes running through the entire project promotion. Help the construction of the project to speed up. (Reporter Yao Wenfeng Zhang Yujie Liu Yingxian reported by Hou Qingping, a reporter from Rizhao Newspaper, reported)

- END -

Hebei Judicial Administrative System Holds International Anti -Drug Day Propaganda Activities

On June 26, the Department of Justice of Hebei Province and the Hebei Provincia...

Jinda County builds emergency rescue "red dam"

From the evening of August 12th to the early morning of the 13th, there was a heav...