Hurry up!The entire train of the northern section of Line 5 is launched!
Author:Hefei Daily Time:2022.08.27
On August 26, a row of motorcycles set off from Tongcheng South Road Station to Jiqiao Road Station, marking the successful completion of the north section of Line 5 (Tongcheng South Road Station to Jaqiao Road Station). The initial operation of the operation is "near".
In order to successfully realize the goal of the node of the northern section of Line 5, Hefei Rail Group conducted three thermal slip tests in accordance with the principle of "mature section, testing for a section".
On August 10th, the hot and slippery test from Tongcheng South Road Station (inclusive) to Huangshan Road Station (excluding) section was conducted. On the 25th, the Mengcheng Road Station (excluding) to the hot and slippery test of the section of the entry and exit section. The length of the hot and slippery range was about 17.3 kilometers.
Motor passenger cars were tested at low, medium and high speeds, and the operating speed reached the highest design speed. During the test process, the relationship between the wheel track and the bow network was normal, the power supply equipment was good, and the design specifications were met. Pilot projects.
After the hot slip test is completed, the Hefei Rail Group will continue to carry out dynamic tests and debts of vehicles, communications, and signal systems, and joint testing of each professional, laying the foundation for the trial operation of the northern section of Line 5.
Wen Tu | All Media Reporter Wang Junchao
Edit | All media editors Han Jie
Produced | "Politics is undergoing" melting media studios, "Lakeside Points" Rong Media Studio
- END -
[Persist in the people's first] Gaoyang Public Security launches a unified operation of summer night public security inspections
Summer night public security inspection and publicity and defense concentrated uni...
Chinese decision: sanctions!pause!
A spokesman for the Ministry of Foreign Affairs announced that China implemented s...