4 lanes become 6 lanes!Gaoke East Road (East China Road -outer Ring Road) Rebellion project enters the main construction stage of the road
Author:Pudong Observation Time:2022.06.18
Recently, the first phase of Gu Tang Road to the East China Road section of Gaoke East Road (East China Road -outer Ring Road) renovated project (temporarily moved the motor lanes to the north side of the road), marking the official opening of the project's main construction phase of the road main construction stage Essence
Project construction press the "Acceleration Key"
Earlier, despite the impact of the epidemic, the reconstruction of the High -Key East Road (East China Road -outer Ring Road) was suspended, but participants still planned in advance to prepare people, materials, and machine preparations to stabilize the construction team. Shanghai Pudong Engineering Construction Management Co., Ltd. actively promotes the relevant construction approval procedures. With the support of the relevant parties, it will be successfully approved for construction land planning permits, construction project planning permits, and road engineering construction permits with only 8 days. On the 24th, it was included in the "List of Re -production and Re -production of the Construction Site of the Pudong New Area" (third batch). Under the premise of coordinating the prevention and control of the epidemic and the construction of the project, the project construction starts from the end of May, the project construction has quickly switched from the "suspension key" to the "acceleration key", and the time and progress of the losses during the epidemic period have been fully switched to the "acceleration key".
Schematic diagram of the scope of project reconstruction
On the basis of strictly obeying the definition and normalized epidemic prevention and control, and safety production, the item of the items will be thoroughly arranged for the construction plan, actively connect with the traffic police detachment construction plan, and timely inspect and guide the progress of on -site construction. The project launched green relocation on June 1st, launched pipeline relocation on June 2, the construction of traffic trails was implemented on June 3, and the concrete pouring and maintenance were completed on June 6. Turn over.
Expand from two -way 4 lanes to two -way 6 lanes
Earlier, the high -tech middle road west of the outer ring has completed the reconstruction of two -way 6 -lanes. This time the reconstruction project of the High -Key East Road, from the west and outer ring roads and east to East China Road, the total length is about 3.5 kilometers, and it includes the local reconstruction of the intersection of East China Road and High -Key East Road. Engineering construction content includes road engineering, bridge engineering, rain sewage pipeline projects, river engineering and green lines, as well as subsidiary projects such as lighting, co -rods, and transportation facilities.
Project renderings
Dai Feng, the manager of the reconstruction project of Hi -Keyong Road, Shanghai Pudong Engineering Construction Management Co., Ltd., said that in addition to the renovation of the road from the current two -way 4 lanes to two -way 6 lanes, the roadbed and pavement will also be re -construction to solve the existing roads of the existing roads. Poward problems such as pit ponds, ruts. At the same time, the four bridges involved along the road will also be transformed or new. Among them, Tangzhen Youyi River Bridge, Caojiagou Bridge, and Central River Bridge are the current bridge to broaden the use of use, and the new bridge is the Xikheng Port Bridge.
It is understood that this reconstruction needs to be implemented within the width of the current red line on the road of High -Key East Road. According to the principle of "borrow one and one", the overall 4 fast and 2 slow lane scale must be maintained during the construction period of the road. The construction site is limited and the complicated traffic organizations are difficult.
On the north side of the road near East China Road, two motor lanes were formed on the newly laid cement road surface. The original road on the south side was implemented, which is about to be transformed.
"Cement pavement is just a temporary construction lane in order to facilitate the reconstruction and construction of the south road. At present, the main implementation of about 800 meters from East China Road to Gu Tang Road on the east side of the project and the flip of about 800 meters from Tang'an Road to the outer ring on the west side of the project. Fai. "Jiang Feng, the project leader of the General Contracting Department of Shanghai Construction Engineering, said that during the entire construction process, different sizes will be scheduled to arrange 6 times to be scheduled for sidewalks, non -motorized lanes, and side bands on both sides of the road. And the construction conditions of the construction of motor lanes. "During the construction process, please also ask citizens and drivers to pay attention to changes in the traffic identification line along the road to ensure the safety of travel."
As an east -west ground traffic trunk in the middle of the Longdong Elevator and the Huaxia Elevator, the reconstruction plan of Gaoke East Road is planned to be completed in September 2023. After the reconstruction, the road traffic capacity will be significantly improved, which will facilitate the transportation of transportation in Tangzhen and Zhangjiang Science City along the line.
Responsible editor Deng Qingyuan
Source Pudong released
- END -
Xinjiang: Standardized planting, fruit farmers' pockets are drumming up
Reporter Cao HuaSome people say that forest fruit planting is simple, a tree seedl...
Welcome to the 20th National Congress of Drugs in Actions -Longqiao Town, Longhua District to carry out the promotional activity of "Do not allow drugs to enter the campus"
In order to further strengthen the school's anti -drug propaganda and education wo...