Natural gas power generation and load are available for 3 million families. Sichuan Investment Yang Gas Power Station project war high temperature grab progress
Author:Ziyang released Time:2022.08.24
Since August, Ziyang has encountered continuous high temperature and drought weather, and the lack of water has led to a decline in power generation capacity. In addition, in the third quarter, it is the golden period for economics, construction, and development.
In this context, the project of the Ziyang Gas Power Station of Sichuan Investment Group with a stable power grid has attracted much attention. What is the progress of the project construction? When will it be built? What convenience can they bring in the future? With questions, on August 23, the reporter entered the project construction site in Yongshun Town, Anyue County to find out.
At 2 pm, the outdoor temperature had exceeded 40 ° C, but the project site was still hot. Before Yan Tianyuan had time to eat a box lunch, he was called to the construction site. Over the past month, this is the normal work normal manager of this Chuanhu (Ziyang) Gas Power Generation Co., Ltd..
"It is expected to complete the project at the end of October." As one of the key projects of Anyue County, the new project of the Ziyang Gas Power Station of Sichuan Investment Group will be officially launched in July this year, and it is expected to be under 2024. After the production, the annual power generation of the project can reach 7 billion kWh, which can be used for 3 million household production and life, which is equivalent to 8 times the current population of Anyue County.
Yan Tianyuan did not dare to neglect at all. On July 13, just after getting the construction order, he came to the construction site to perform flat operations with his colleagues. Continuous high temperature weather has increased the difficulty of project site construction. "The temperature is as high as 40 ° C, and the outdoor operation is not safe." In order to take into account the progress of the health and project construction of the construction personnel, Yan Tianyuan and the team decided: construction, night operations, and rolling classes.
High temperature is not the only problem facing the project, and there is still a situation of power shortage at the scene. To this end, the construction party not only purchased the diesel generator, but also applied to the State Net Ziyang Power Supply Company for deploying an emergency electric car to further ensure construction power.
In order to accelerate the progress of the project, while the construction parties also started the construction of the main factory and the pile foundation of the residual heat boiler. "It is expected that the concrete pouring of the main factory can be started at the end of September. The venue is flat in October, and the construction of the supply water project outside the plant will be achieved in November." Yan Tianyuan is full of confidence in the progress of the project construction.
Pan Zhengji Ai Lanhua
- END -
Due to persuasion, dining and starting a business, don’t touch these 5 categories again
In a complicated and uncertain environment, catering startups still need to be cautious, especially to avoid some tracks that are destined to die for a lifetime.The changes in the environment make the
Hu Li Notice: For 10,307 people in the jurisdiction!
According to the Announcement on the Related Matters of All Nucleic acid Testing i...