Yanji newly built 3 roads today to test the traffic at the same time at the same time
Author:Yanji Propaganda Time:2022.08.24
After more than 800 days of construction, with the eager expectations of the citizens, the fourth phase of the Central Road in Yanji City, the extension of Yanhe Road, and the Xishan Street project have been tested to the train this morning. The "unblocked all the way" on the road.
Photo by Wang Xiaotong for the fourth phase of Central Road
Try to open the fourth phase of Central Road, unblocked by Wang Xiaotong
Photo by Wang Xiaotong, extended road section of Yanhe Road, which was opened
Try to open Xishan Street section
At the fourth phase section of Central Road, the reporter followed the test of 30 kilometers per hour in the trial speed limit to the direction of Suzhou's impression on the intersection of Park Road and Jinsley Street on the east side of the state government. The fourth phase of the Central Road in Central was spacious and stable. The traffic time was less than ten minutes, which greatly improved the efficiency of traffic.
"I was really happy to open the fourth phase of Central Road as a taxi driver. I could only take the park road before and often traffic jams. After opening, I went directly to the fourth phase of Central Road. It ’s really two fixes.” Mr. Wang, a taxi driver, praised the opening of the fourth phase of Central Road.
Mr. Lu, who lives in the first issue of Suzhou, also praised the opening of the fourth phase of Central Road. He said that the opening of the fourth phase of Central Road has brought great convenience to surrounding residents. It is more convenient to go to Yanji West Station, state governments, and stadiums, and truly benefit the people.
The extension of Yanhe Road is an important section of the rapid arrival of Yanji West Station and the stadium. It starts from Xinmin North Street in the east and the west to Yanchuan North Street with a total length of 2.4 kilometers. After opening, the traffic time is only about 5 to 6 minutes.
The starting point of Xishan Street project began on the north side of the east gate of Yanbian University. The end point and the fourth phase of the road in Central Road were integrated. The total length of construction was 1940 meters. After opening, the traffic time is only about 3 to 4 minutes.
- END -
Tongyu County Meteorological Bureau to remove hail yellow warning [III level/heavier]
At 21:35 on June 8, 2022, Tongyu County Meteorological Bureau lifted the hail yellow warning signal.
Two of the Henan Supervision Bureau of the Banking Insurance Regulatory Commission was investigated
Jiang Honghua, Director of the Policy and Regulations Division of the Henan Superv...