From August 20th, the construction of some sections of Shijiazhuang Yubai Street
Author:Hebei Radio and Television Sta Time:2022.08.19
Provincial capital Yucai Street (Zhongshan Road to Fangbei Road) Drainage Pipeline Transformation Project Construction During the Construction of Traffic Organization
The reconstruction of the drainage pipeline of Yucai Street (Zhongshan Road to Fangbei Road) is scheduled to start at 22:00 on August 20, 2022 (Saturday).
1. Construction time
From August 20th to October 20th, 2022, the construction period was two months.
2. Construction method and traffic organization
The current road of closed Yucai Street (Zhongshan Road to Fangbei Road) is available for construction. During the construction period, motor vehicles are prohibited from passing.Ensure that Zhongshan Road and Yucai Street East and West, east and west of the northwest of the east and west.At the same time, the construction progress of Fangbei Road and Yucai Street exit drainage pipes are connected according to the construction progress of the road section.
- END -
Power supply: abide by the safety production method to keep the safety lifestyle
On June 14, the State Grid's Power Supply Company of the State Grid produced a saf...
One picture understands | The latest epidemic prevention and control of Chengdu: 3 cases of 11 asymptomatic infected in the local diagnosis
Cover reporter Lai Fangjie Wang Haoyan Su Jiaxin intern on behalf of Jianglan