The city's newly converted 135 power distribution transformers to benefit 22,000 households
Author:Changjiang Daily Time:2022.08.12
The Yangtze River Daily Da Wuhan Client August 12 (Reporter Liang Shuang Correspondent Wang Xin) Wuhan's temperature rising festival, is it enough power supply that is closely related to the lives of citizens? On August 11, the reporter learned from the State Grid Wuhan Power Supply Company that it is solving the possible user -ending power quality problem of the user's terminal by temporary new power distribution transformers to fully protect the reliable power supply of the world. New and reconstruction of power distribution transformers.
At the same time, in order to cope with the continuous high temperature weather this year, Wuhan's power supply department is passing through a number of measures such as special patrols, drone inspections, and high -voltage line obstacles. Stable supply provides effective support.
High -temperature sky temporary new transformer protection electricity
At high temperature, the power supply personnel repair the transformer. Correspondent Wang Xinxin
"In the high temperature in early July, the power supply situation in our community was very tense. Fortunately, a transformer was installed soon." Master Wang, a resident of Liqiao Community, introduced that this year's high temperature weather came early and fiercely. The way to put forward the demand for the power supply point to the power supply department.
After the feedback from the residents of the Liqiao community, Wuhan Power Supply Company Wuchang Power Supply Company, immediately sent someone to the scene for survey and found that the original 630 kV of the Liqiao 4 districts here can no longer be satisfied In order to ensure the stable power consumption of residents in the hot weather, the company added a 630 kV power distribution transformer to this community on July 19 to ensure that it can meet the economical efficiency Operating conditions, thereby greatly improving the quality of electricity consumption of residents.
Power supply personnel repair the transformer. Correspondent Wang Xinxin
Measures such as transformer installation in the terminal of power supply services are one of the practice methods of Wuhan Power Supply Company to carry out low -voltage monitoring and governance this summer. According to reports, in this year's high temperature, the company has temporarily applied to reserve 30 various types of power distribution transformers to ensure the power consumption quality of the terminal.
Zhang Min, the power distribution department of the State Grid Wuhan Power Supply Company, introduced that in the summer of this summer, they have completed a high -altitude inspection of more than a hundred power supply lines in various jurisdictions. The report is based on the analysis of relevant departments and fundamentally solve the line problem.
At the same time, in order to ensure the efficiency as much as possible at the scene, Wuhan Power Supply Department also uses various advanced mobile power equipment such as robotic operations, 10 kV mobile power vehicles, emergency power vehicles, and energy storage vehicles. Such high -tech is also applied to a number of improved regional power supply quality such as substation's parent line maintenance and transformer increase in the platform area, helping to stabilize power supply.
Newly reconstructed transformers to benefit 22,000 households
It is understood that before the high temperature arrived this summer, Wuhan had completed the new and reconstruction of 135 power distribution transformers, with a capacity of 47,000 kV, which benefited 22,000 households.
State Grid Wuhan Power Supply Company introduced that the construction of the company's distribution network has continued to make efforts. Since the beginning of this year, 135 power distribution transformers have been rebuilt through the distribution network project, with a capacity of 47,000 kV. At the same time, the total mileage of new and transforming the power supply line is 332 kilometers. The 10 kV lines are 170 kilometers and the low -voltage line is 162 kilometers.
In addition, before the peak summer arrived, the power supply department completed a total of 24 10 kV lines such as the Yujia head and Zhaojiabou, which provided a strong guarantee for the stable power supply during the peak period of the summer power consumption.
The new and reconstructed routes provide strong support for the power grid, which also makes daily operations more important. The reporter learned that as of now, the State Grid Wuhan Power Supply Company has completed a total of 1,600 lines of special patrol during high temperature this summer to ensure the normal electricity consumption of residents.
At present, the State Grid Wuhan Power Supply Company continues to strengthen the 24 -hour duty system during the peak summer. More than 170 emergency arranged warranty teams, more than 2,400 personnel on duty, and more than 400 vehicles to repair them to ensure that emergency response can be responded to emergency failures and quickly restore power supply.
[Edit: Deng La Xiu]
For more exciting content, please download the "Da Wuhan" client in the major application markets.
- END -
We have never slackened this big event!
June this yearIt is the 21st national Safety Production MonthChina RailwayCombined...
Originally wanted to make South China heavy rain move down, but it made Shandong collapse ... Where will the heavy rain go after that?
When South China was trapped in the storm of heavy rain some time agoEveryone is w...