Xiamen Metro Line 6 has made new progress!

Author:Xiamen Daily Time:2022.08.08

地铁项目现场,已经贯通的盾构区间。

The subway project site, the shield interval.

A few days ago, two key nodes of Xiamen Metro Line 6 Corporal Extended Section have made breakthrough progress: operating at Shentou Station -Linyuxi Station (Xiamen) Shield "Longjiang No. 11" successfully launched, this should be The interval is connected to the Xiamen section; the "Longjiang No. 8" shield machine successfully crossed the thick sand in the high water level to go out smoothly, achieving the goal of the turtlewen interval (that is, Guishan Station -Wenpu Road Station).

The "Longjiang No. 11" has been excavated by 1046.6 meters on the right line, and it is expected to achieve hole in February next year. Wearing an important structure such as the viaduct and power supply cable in the community of the community in the community of the community. Later, connected to Xiamen Metro Line 6, and the construction was difficult. Participants have organized experts to optimize construction plans and emergency plans for many times, and repeatedly conducted repeatedly Research. The excavation of the interval uses a composite soil pressure balance shield machine to meet the requirements of complex strata and environmental protection to ensure that the shield machine is safe and smooth.

Xiamen Metro Line 6 Horn 6 extends 9.8 kilometers in length, among which 8.2 kilometers in Zhangzhou, 1.6 kilometers in Xiamen (from the west of Linxian to the junction of Kokmei). 7 stations, Kumishan Station, Wenpu Road Station, Jiaohai Road Station, and Shentou Station. At present, the overall engineering plan is promoted in an orderly manner, and the main line has completed 27%of the total investment; the three stations of Guishan Station, Wenpu Road Station, and Xiongtou Station have completed the main structure. The right line of the interval dual -line and the turtle interval has been connected, and 7 shield machines in the entire line are excavated.

(Text/Tu Xiamen Daily Special Reporter Huangshu Jinlin Senquan)

- END -

The chairman of the Provincial People's Congress Standing Committee chaired by Wang Ning

On June 17, the 107th chairman of the Standing Committee of the 13th Provincial Pe...

Shandong: Focus on strengthening key technologies in the industry and accelerate the realization of high -level technology self -reliance

This morning, the Provincial Government News Office held the third session of the ...