The epidemic prevention and control is not relaxed, and the rapid progress of the rapid channel of the Yangtze River Road is steadily advanced.
Author:Heze Daily Time:2022.08.08
At present, our city has entered a "consolidation period" of the prevention and control of epidemic. As a key engineering construction project, under the premise of doing a good job of preventing and controlling the epidemic, the Changjiang Road Expressway Project competed for the times and rushed to rush the progress of the work.
On August 6, the reporter visited the construction site of the Changjiang Road Express Channel Project (Guiling Road to Wuhan Road). The road section reached traffic conditions on the 20th of this month. According to the on -site construction staff, in order to ensure the progress of the project and the construction of the project during the epidemic, employees participate in nucleic acid testing and inspection daily.
Since July 25, as of yesterday, the Yangtze River Road Express Channel Project has completed a total of 22 pile bases, 16 pouring in Chengtai, 31 prefabricated columns, 12 pieces of cover beams, 32 box beams, and 11 pieces of lids.
The reporter learned from the Municipal Housing and Urban Construction Bureau that during the epidemic situation, the Tongjiang Road Engineering Construction Headquarters set up a temporary management team to launch an emergency plan. All personnel were on their jobs all the time to check the implementation of the epidemic prevention measures for each site site, and coordinated the relevant enterprises to do a good job of steel bars, and Reserve and supply of concrete production raw materials. Among them, the two prefabricated fields are fully closed. The project workers need to go out and reduce the risk of epidemic conditions; apply real -name face recognition system, "brush the face" identification information of the entrance and exit site, automatically detect health code and body temperature. It is strictly not related to it. Personnel enter. At the same time, daily nucleic acid tests are strictly implemented to ensure that one person does not fall. In order to ensure the transportation during the prevention and control of the epidemic, the project adopts a 24 -hour continuous construction method to fully speed up the construction of Guiling Road from the Expressway from Changjiang Road to Wuhan.
Heze Pay Industry All Media Reporter Jiang Lulu
- END -
Qingshui in Gansu: Vegetable greenhouse harvesting rural revitalization industry prosperous
The red purple has become dusty, and the summer is new. In the midsummer season of...
Lintong District Xinshi Street Community Games Jumping Project Tournament Trial Opening
On June 28, the new street community community skipping selection competition started, and more than 30 skip rope enthusiasts from the jurisdiction participated in it.The competition was played in the