Total investment is about 80 million yuan!Huangshi will have a big change here

Author:Yellowstone release Time:2022.08.07

latest news

Hangzhou West Road crowded road renovation project

Start construction

Hangzhou West Road is located in the center of Tuancheng Mountain. It starts from Magnetic Lake Road in the west and the south and north roads in Guilin in the east. It is about 2.7 kilometers in length. The total investment of the Hangzhou West Road Sideline Reconstruction Project is about 80 million yuan. The main content involves the update of the sidewalk breaking the new construction, urban furniture (that is, various outdoor environment facilities in the city), the reconstruction of the harbor bus station, the greening landscape along the line, and the improvement of the greening landscape, and the improvement of the green landscape, and the improvement of the green landscape, and the improvement of the green landscape, and the improvement of the green landscape, and the improvement of the green landscape, and the improvement of the green landscape, and the improvement of the green landscape, and the improvement of the green landscape, and the improvement of the green landscape, and the improvement of the green landscape, and the improvement of the green landscape, and the improvement of the green landscape, and the promotion of the green landscape, and The construction of pocket parks and the planning of parking spaces along the line.

What is the progress of the project?

Take a look

engineering design:

The project design plan has been reviewed by the Municipal Planning Committee on May 27, 2022, and the construction drawing design has been completed.

Construction plan:

The project is responsible for the construction of the Guizhou Engineering Company of China Electricity Construction Group, and it is divided into 8 construction sections throughout the board.

From August 4th to October 11th, 2022, the south side of the Hangzhou West Road has closed the sidewalk;

From October 12th to December 31st, 2022, the sidewalk on the north side of Hangzhou West Road was closed.

At present, the construction unit has begun the installation of the sidewalk construction sidewalk on the south side of Hangzhou West Road.

Warm reminder of the construction bureau of the lower land area:

During the construction period, the fence management of the work surface will be closed according to the actual situation. It is hoped that the shops, residents, and pedestrians along the line must be vigilant and pay attention to their own safety when the construction site is under construction site. At the same time, we must reasonably arrange construction time to accelerate the progress of construction under the premise of ensuring safety and quality. Due to the inconvenience caused by construction, please forgive and support the general public!

- END -

"Coco Tuohai My Soul" large -scale drama Altay premiere

Reporter Zhang TingOn the stage, under the warm yellow light, an old man who was s...

[Core Mission 2022] Harbin Traffic Police strongly rectifies the chaos of static parking, strictly fights drunk drunk driving, card involved in card involved, chasing competition, and other high -risk violations

National Civilization City is the city brand with the highest gold content, the mo...