Let Daonan high -speed rail along the river, the 98 -meter bridge and the largest toll station in Nanjing lasted 36 hours to successfully remove
Author:Nanjing Morning Post Time:2022.08.06
On the morning of August 6th, in the roar of more than 150 machinery, the cross -growth and deep high -speed highway Yuehua Road Bridge and Nanjing charging station in Jiangning District, Nanjing City successfully implemented the mechanical demolition under the operation of the builders of China Railway Fourth Bureau. The deep high -speed parallel section is changed to provide guarantee for the opening of the intercity railway of the south along the river.
Changshen High Speed (G25) Nanjing to Hangzhou section is Ninghang Highway. This line is an important transportation line for the long triangle of Shanghai, Soviet Union, Zhejiang, and Zhejiang. It is an important fast channel connecting Jiangsu and Zhejiang's two economic provinces. Among them, Yuehua Road, Jiangning District, Nanjing, cross -growing high speeds in the form of bridges, is divided into left and right, 32 meters wide and 98.36 meters in length. The status quo is six advances and twelve out, 85 meters wide, 22 meters long, 15.5 meters high.
"Because the Changshen Expressway is too close to the distance between the intercity railway of the Jiangsu south along the river, it does not meet the requirements of the railway safety red line distance. The toll station greenhouse will be demolished and rebuilt. "Jia Kai, the manager of the Shenzhen Railway Fourth Director's Shenzhen High -speed Paying Section, introduced that from 6 o'clock on the morning of August 6, Changshen High -speed Shangfang Interchange and Lakes and Hubo -Condor Section (two -way) closed 24 hours, Dongshan hub to Shangfang interconnected section (Hangzhou to Nanjing) closed and closed for 36 hours. The traffic flow of the Changshen Expressway (Nanjing section) is huge, with a daily section mixed traffic of nearly 60,000 vehicles. The project department will publicize and remind them on local media, map software, and local trunk roads one week in advance. Complete the demolition work in the shortest time to reduce the influence of the traffic road network in the southern Jiangsu region.
Lu Fangmin, deputy general manager of Jiangsu Nanfangjiang Intercity Railway Co., Ltd., said that on the highway with such huge traffic flows at the same time, the 98 -meter bridge and the largest and busiest toll station in Nanjing are at the same time. It is the first case in high -speed construction. The demolition process directly affects the normal operation of the two highways of long -depth (Ninghang) and around the city. During this period, more than 500 people were dispatched through units such as joint high -speed traffic police, local traffic police, local road administration, and actively did a good job of road preservation and epidemic prevention and control during the closed construction period.
At 6 in the morning, more than 150 crusher, loader, car crane, and residue cars were strictly waiting next to Yuehua Road and Bridge and Nanjing toll stations. In order to ensure the smooth construction, the China Railway Fourth Director's Shenzhen High -speed Paying Section was renamed the project department in advance and tightly deployed it, and organized experts to discuss and technical demonstrations. A comprehensive safety emergency security system is ensured to ensure that the demolition process is safe and orderly.
Jia Kai introduced that the risk of continuous operations under high temperature weather was high. The project department distributed the heatstroke cooling drugs such as Huoxiangzheng Qi and Ren Dan in advance. Hand -in -turn operation, two ambulances were prepared at the scene, and a linkage mechanism was established with recent hospitals. The leadership team of the project department was 24 -hour. Safety officers and protectors were inspected at any time to ensure the health of the operator.
It is reported that the newly -built Nanjiang Intercity Railway is an important backbone line in the planning of the comprehensive three -dimensional traffic corridor of the Yangtze River Economic Belt. The design speed is 350 kilometers per hour. The new positive line length is about 278 kilometers. After the inter -passenger flow, after the line is completed, Jurong, Jintan, Jiangyin, Zhangjiagang, Changshu and other famous counties along the line will accelerate the integration of the Shanghai -Ningxin high -speed rail circle.
Correspondent Su Tiexuan Su Shiyang Su Dingyi
Nanjing Morning Post/Ai Nanjing reporter Chen Yan Xinhua A visible center reporter Zhao Yaling
- END -
Innovation measures in Luyang Street to implement the "five -star" branch
Recently, the Party Committee of Luyang Street in Lushan County established Luyang...
Sudden!8 people have been injured, and 6 people have lost contact
The reporter learned from the relevant departments of Gansu Province that at 18:50...