Dahe Tao 丨 The overall project completed 40% of the construction of the Great Stone Gorge Water Conservancy Hub into the "Running on the way"
Author:Tianshan.com Time:2022.08.05
Tianshan News (Reporter Cao Hua reported) "The construction scale of the Xinjiang Dashixia Water Conservancy Hub has completed 40%of the overall project. At present, it is stepping up the construction tasks such as stacking stone dams, water diversion and power generation systems, and water leakage and sandwiches. "On July 30, Li Songlin, deputy director of the engineering management department of Gezhouba Dashixia Water Conservancy Water Conservancy Institute of Xinjiang, said.
The dam at the bottom of the valley fills the scene. Pomegranate cloud/Xinjiang Daily reporter Cao Hua Photo
The Xinjiang Dashixia Water Conservancy Project is located at the Dashixia Canyon River at the junction of Wensu County and Wushi County in Aksu. The hub project is a major water conservancy project for water -saving water supply. After completion, the reservoir library capacity is 1.17 billion cubic meters, the power station installed capacity is 750,000 kilowatts, and the annual power generation is expected to be 1.89 billion kWh. The main task of the project is to supply water to the dry flow of the Tarim River, take into account the comprehensive functions of irrigation and flood control, and shoulder the mission of power adjustment in the four places in the southern Xinjiang. At present, about 1,800 construction workers are fighting at the construction site of the Dashixia Water Conservancy Hub in Xinjiang.
The reporter saw at the construction site that a busy scene at the dam at the scene of the dam, and the team that transported the filling materials ranked into a "long dragon". Workers carry out concrete construction in power plant buildings, flood roads and other parts, and the installation of pressure steel pipes is also promoted in an orderly manner.
The construction site of the power station plant and the water diversion hole. Pomegranate cloud/Xinjiang Daily reporter Cao Hua Photo
Li Songlin introduced that the main project of the Dashi Gorge Water Conservancy Hub in Xinjiang started in November 2019 and was planned to be completed in October 2026. At present, all working surfaces such as dams, power stations, and water leakage and sand exhaust systems are "full flowers". Among them, the concrete panel gravel dam with 247 meters high, the filling has reached 52 meters, which is equivalent to the height of the 18 -story building. It is expected to complete the second phase of the dam next year. High -speed; Power station plant is undergoing concrete pouring and basic structure installation. The three power generation water caves have been connected. At present, pressure steel pipes are installed, and flood -flooding buildings are pouring flooding channels.
At the metal structure manufacturing workshop not far from the construction site, technical workers processed pressure steel pipes with a diameter of 6 meters in an orderly manner. The completed steel pipes were transferred to the stacking area for rust and anticorrosion, waiting for the project to play a role. "A total of 3 diversion holes of the Dazhi Gorge Water Conservancy Project in Xinjiang, with a length of 683 meters, 701 meters, and 720 meters. Entering the generator room for power generation. "Peng Benrong, deputy chief engineer of the Xinjiang Dashixia III standard project department of Xinjiang Dashixia III, China Nengjian Gezhouba Group, said that the current pressure steel pipe has produced more than 8,000 tons to ensure the installation progress.
"In order to ensure the steady advancement of the construction of the Dazhi Gorge Water Conservancy Hub in Xinjiang, we have adopted a series of scientific management methods. In design, three -dimensional three -dimensional design can be used to understand the project more intuitive, comprehensive, and thoroughly. In addition, the project construction process The development of digital construction technology, the operation, mixing, quantity, temperature, and personnel activities of personnel are collected and organized. What do you do every day, place location, how much you complete, and how to make progress can be clear at a glance, ensuring that the entire entire is ensured, and the whole of the entire management system can be ensured that the entire entire is ensured that the entire entire The work link is accurate and orderly. "Zhou Junfang, chief engineer of the Gezhouba Dashixia Water Conservancy Development Co., Ltd., Xinjiang, said," Through scientific management, the processes of Xinjiang Dashixia Water Conservancy Hub have been fully launched. Long -distance runners have entered a stable "run", and the rest are step by step, steadily fight, and successfully achieve the goal of completion in 2026. I am full of confidence in this. "
- END -
"Party Member Red" guards the "ancient tree green" -the side of the centennial tea tree on the creek bay
Reporter Jiao GuobinListingOn July 14, the sun was hot. The staff of the Agricultu...
"Iron" full record 埃 Railway Engineering Logistics: Crossing the mountains and the sea come to the sea (Chinese and English)
Logistics for the 10th of Ramadan Railway Project in Egypt: Safe and Efficient Del...