The Yangtze River Daily Da Wuhan Client June 16th News On the morning of the 16th, the first beam of the Lake Bridge Reconstruction Project in the Tsuki Tsui was successfully lifted in place, marking that the important project of this "hard Unicom" of Wu Ewan entered the upper structure of the bridge. After the completion of the future, it will greatly enhance the ability of the two places to promote the "transportation of the same network" and regional economic development in the same urbanization of Wu'u.
The project is constructed by Wuhan Optics Valley Construction Investment Co., Ltd., and the China Railway Bridge Bureau is undertaken.
After the renovation of the lake and bridge in the short peak. (Correspondent Yu Yajuan Picture)
On the same day, the reporter from the Yangtze River Daily saw at the scene that the lake and bridge in the original short peak remained normal, and there were many vehicles that were connected to and from. Especially during the morning peak hours in the morning, the vehicles were slow. Optics Valley lives in Gejian to work, or lives in Ge shop in Optics Valley. This bridge is the way they must go to work.
After the renovation of the lake and bridge in the short peak. (Correspondent Yu Yajuan Picture)
Wang Chunguang, executive deputy chief engineer of the China Railway Bridge Bureau project, introduced that if it is bypassing other roads to the Gejian Development Zone, it may take about ten kilometers. Therefore, this road has more than a thousand vehicles per hour during the early peak hours, which is very busy.
With the transformation of the high -tech avenue, the two -way 8 -lane main road extends to the side of the bridge, and the roads are narrowed here. The original bridge can no longer meet the traffic needs, and it is urgent to transform. The transformed bridge will broaden the two -way 8 lanes. Set up 5 meters of non -motorized lanes and sidewalks on both sides. It is perfectly connected to the high -tech avenue. On both sides of the bridge, you can also enjoy the scenery of the lake in the short peak.
The first beam of the lake and bridge renovation project in the short peak is being lifted. (Correspondent Yu Yajuan Picture)
The reporter saw that on both sides of the bridge with a total length of 926.06 meters, the construction of the bridge was underway. Among them, the basic construction of the widening bridge pier on the south side was completed. The first beam body was set up between two pier. The construction of the bridge deck adopts the "prefabricated and stitching" process. The 7 prefabricated beams will be tied to rows on the bridge pier. This method not only ensures the quality of the beam body, but also guarantees the overall construction progress.
The two cranes "cooperated" to complete the construction of the first beam of the lake and bridge renovation project in the short peak. Reporter Gong Ping Photo
Wang Chunguang introduced that the appearance design of the bridge is "infinite" as the creativity. The steel arch of the main bridge is interconnected on the space, which means the infinite possibilities of the East Lake High -tech Zone and the heart of open development. The bridge will also be brightened, becoming a bridge with both landscape landmarks. Not only can it effectively connect to regional transit passenger transportation, but also provides a slow -moving passage of regional, convenient, and comfort that spanning the lake in the short peak, providing a comfortable space for surrounding citizens to rest and watch.
(Changjiang Daily Reporter Gong Ping Correspondent Huang Jian He Junyan)
【Edit: Zheng Xiaoxiao】
For more exciting content, please download the "Da Wuhan" client in the major application markets.
- END -
When will the extreme weather continue to "southern rainstorm+high temperature in the north"?Expert explanation
Jimu Journalist Li XianchengRecently, netizens in the south and north felt complet...
Pack money!The end of this month!
Pay attention!Or you can withdraw money!The deadline at the end of this month!Acco...