Look at it!This important road is expected to be released at the end of the year

Author:Hefei Daily Time:2022.08.02

On the morning of August 2nd, the construction site of the 5th bidding section of the Bao Gong Avenue (Twenty -Twenty River -Longxing Avenue) project was hot, and the workers were seizing the current clear weather to accelerate the construction. At present, the bid section has completed the construction of the main road lane water stability and the construction of the structure of the structure. The next step will be constructed by the auxiliary of the bridge surface and the asphalt construction of the road under the bridge.

Bao Gong Avenue (Twenty River-Longxing Avenue) project starts from 20 ports in the west and Longxing Avenue in the east. The total length of the road is about 15.5 kilometers, the main bridge is about 11.7 kilometers long, and the road red line is 55-60 meters wide. A total of five bid sections are divided into construction.

On the morning of August 2nd, the 5th bid section of the project of Aerospace Baogong Avenue (Twenty Butu River -Longxing Avenue). Photo by Song Yanjun, all media reporter Song Yanjun

The project is constructed as a whole in the form of ground expressway+elevated fast roads. Among them,: 20 kilometers long to Yunjin Road section: Twenty-port to Yunjin Road. The length is about 11.7 kilometers and uses an elevated expressway. In addition, at Wenzhong Road, Qiaotou Ji Road, and Longxing Avenue, the interchange interchange is set up to achieve rapid conversion.

On the morning of August 2nd, the 5th bid section of the project of Aerospace Baogong Avenue (Twenty Butu River -Longxing Avenue). Photo by Song Yanjun, all media reporter Song Yanjun

The reporter's on -site interview was informed that the project's soil and stone project was completed with 88.8%, the pile foundation was completed 98.7%, the main line of the pyrine beam was 94.6%, and more than 70%of the total project volume has been completed. The construction and pipeline construction of the upper and lower parts of the bridge is currently underway. According to the plan, the main structure of the main bridge will be completed in August (except for the shops of the shop of the shop), and some sections are expected to release at the end of the year.

On the morning of August 2nd, the 5th bid section of the project of Aerospace Baogong Avenue (Twenty Butu River -Longxing Avenue). Photo by Song Yanjun, all media reporter Song Yanjun

After the project is completed, it can be seamlessly connected through Longxing Avenue, Hengbang Road and Hefei Ring City High Speed, Jingtai high -speed, and can also easily contact the important countries and provinces such as G329 and S105 to achieve the central city and foreign traffic networks. Quickly connect.

On the morning of August 2nd, the 5th bid section of the project of Aerospace Baogong Avenue (Twenty Butu River -Longxing Avenue). Photo by Song Yanjun, all media reporter Song Yanjun

【News more】 a little more]

What is the progress of the five bid sections of Baogong Avenue? The reporter also sorted out today, as follows:

Baogong Avenue 1

Located in Yaohai District, it is an existing road renovation project. It starts with Xinhai Avenue in the west and the city of moat in the east. The total length of 3.525 kilometers. The standard red line width of the road is 60 meters. At present, the main body of the bridge structure has been completed. The next step will be constructed by the bridge deck. The roads, drainage and asphalt construction under the bridge.

Baogong Avenue 2 standard

It is located on Feidong County, from west to protect the city, and to Guiwang Road in the east, with a total length of 2.902 kilometers. The standard red line width of the road is 60 meters. At present, 72%water stabilization construction, and structural main construction of the main road lanes of the road have been completed. In the next step, the construction of a bridge is asphalt, telescopic joint, and sound barrier.

Baogong Avenue 3 standard

Located on Feidong County, it is a road renovation project, the main line of Baogong Avenue starts from Guiwang Road (97+24), east to Linquan East Road (110+54), and the main line of Qiaotou Road to the north of Qiaotou Road, crossing the store Bridge 0#Bridge (Q2+06), south to Guhe Road (Q13+78), Bao Gong Avenue is 1.33 kilometers in length, and planned red line width of 55-60 meters. At present, the main body of the road base and structure has been completed. In the next step, the construction of the bridge deck will be carried out. The water stabilization of the road under the bridge and the asphalt construction will be carried out.

Baogong Avenue 4

Located on Feidong County, it is an existing road renovation project. It starts from Linquan East Road in the west and unity in the east. The total length of 2.424 kilometers, the standard red line width of the road is 55-60 meters. At present, the construction of the main car lane water stability and the construction of the main body of the road lanes will be basically completed. The next step will be constructed by the bridge deck, asphalt construction on the bridge under the bridge, and traffic lighting construction.

Baogong Avenue 5

Located in Feidong County, it is a road renovation project. It starts from the avenue of unity in the west and the Longxing Avenue in the east. It has a total length of 2.622 kilometers. The standard red line width of the road is 60 meters.Longxing Avenue is 0.925 kilometers in length, and the standard width of the road is 52 meters.At present, the construction of the main road lane water stability and the construction of the structure of the road will be completed. The next step will be constructed by the bridge deck, and the asphalt construction of the road under the bridge will be carried out.Text | All Media Reporter Wang Junchao


Photography | All Media Reporter Song Yanjun

Edit | All media editor Wu Hong

Produced | "Lakeside Point" Rong Media Studio, "See Hefei" Rong Media Studio, "Shanshan is not late" Rong Media Studio

- END -

Go to the Qinghai -Tibet Plateau and see the mistakes!

This articleSecond Qinghai -Tibet Science Examination TeamJointly produced with th...

A group of new rules will be implemented in July, which is related to you and I live

Xinhua News Agency, Beijing, June 30th.Xinhua News Agency reporter Bai YangIn the ...